Cheniere gets more time to build Corpus Christi LNG expansion project

US energy regulators granted Cheniere’s request for more time to build the proposed Stage 3 expansion at its Corpus Christi LNG export plant in Texas.

In December last year, Cheniere filed a motion with the FERC requesting a 31-month
extension of time to complete construction and place the project into service.

“Corpus Christi Liquefaction Stage III, LLC, Corpus Christi Liquefaction, LLC,
and Cheniere Corpus Christi Pipeline, LP are granted a 31-month extension of time to
June 30, 2027, to construct and make available for service the Stage 3 LNG Project,” FERC said in the order dated May 6.

The Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

Under the expansion, Cheniere plans to add up to seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa, with a total production capacity of more than 10 mtpa.

In March, Cheniere awarded a lump sum, turnkey, engineering, procurement and construction contract to compatriot Bechtel for the expansion.

Bechtel has begun early engineering, procurement and other site works under limited notice to proceed.

In addition, Cheniere recently signed a deal with a unit of Canada’s ARC Resources under which the latter will supply natural gas to the Corpus Christi expansion project in Texas.

Cheniere said it expects to reach FID on the expansion this summer.

Most Popular

Golar buys conversion vessel for fourth FLNG

Floating LNG player Golar has agreed to acquire the LNG carrier Grace Dahlia from Japan's NYK Line to convert it into a floating LNG production unit.

Cove Point LNG to resume operations after maintenance

Berkshire Hathaway’s unit BHE GT&S is expected to restart its Cove Point LNG export plant in Maryland soon following planned annual maintenance.

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

Cheniere, Petrobras seal long-term LNG SPA

US LNG exporter Cheniere has signed a long-term LNG sale and purchase agreement with Brazil’s state-owned energy firm Petrobras

US FERC issues final EIS for Cheniere’s Sabine Pass expansion project

The US Federal Energy Regulatory Commission (FERC) has released a final environmental impact statement for Cheniere’s planned Sabine Pass Stage 5 expansion project. The regulator confirmed that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”

FERC issues draft EIS for Cheniere’s Corpus Christi Stage 4 project

The US Federal Energy Regulatory Commission (FERC) has released a draft environmental impact statement for Cheniere’s planned Corpus Christi Liquefaction Stage IV expansion project in Texas. The regulator concluded that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”