Cheniere plans two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is planning to build two more liquefaction trains and one storage tank as part of the third expansion phase at its Corpus Christi LNG export plant in Texas.

The Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June, Cheniere took a final investment decision on Stage 3 expansion at its Corpus Christi LNG export plant.

Under the expansion, Cheniere will add up to seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa, with a total production capacity of more than 10 mtpa.

Cheniere’s chief executive Jack Fusco recently said that the company was working to add over 30 million tonnes of capacity at its Sabine Pass and Corpus Christi plants. These plants now have a combined capacity of more than 45 mtpa.

Fusco said that the company would provide more details on its growth plans at both Sabine Pass and Corpus Christi “later this year”.

Each train to have capacity of 1.64 mtpa

Cheniere revealed more details of the expansion plans at the Corpus Christi plant in a filling with the US FERC filed earlier this month.

The US LNG terminal operator submitted a letter with FERC to initiate the pre-filling process for the proposed Corpus Christi Liquefaction Midscale Trains 8 & 9 Project.

Moreover, the project would be located about 1.6 kilometers southeast of Gregory, Texas and would be integrated adjacent to or within the existing Corpus Christi plant.

It would consist of two midscale liquefaction trains, each capable of producing up to
1.64 mtpa of LNG, on-site refrigerant storage, a 220,000-cbm LNG storage tank, and an increase in the authorized LNG loading rate, according to Cheniere.

Cheniere said it would supply feed gas to the project via a combination of the Corpus Christi pipeline system and a nonjurisdictional intrastate pipeline.

Upon completion of the Commission’s mandatory 6-month pre-filing process, anticipated in
February 2023, Cheniere said it plans to file a formal application to seek authorization of the project no later than August 2024.

Cheniere plans to start construction in October 2024 and to launch the project in the second half of 2031.

Most Popular

Venture Global charters LNG carrier duo

Venture Global has executed two short-term charters for additional LNG tankers. The vessels were delivered in August and September 2024,...

Hudong-Zhonghua launches two LNG tankers

Chinese shipbuilder Hudong-Zhonghua has launched two 174,000-cbm liquefied natural gas (LNG) carriers. According to a statement by Hudong-Zhonghua, the launching...

UAE’s Adnoc, Thailand’s Gulf ink LNG supply deal

State-owned Adnoc said on Monday that Adnoc Trading's LNG desk has recently signed a supply agreement with Thaliand's Gulf...

More News Like This

Cheniere’s Corpus Christi expansion project nears first LNG

According to a filing with the US FERC dated December 20, Corpus Christi Liquefaction requests to introduce FEED gas...

Venture Global gets OK for first Plaquemines LNG commissioning cargo

FERC granted Venture Global Plaquemines LNG's request on December 20 to "export by LNG marine vessels the volumes of...

US DOE releases LNG export study

The Biden administration said in January it will pause pending decisions on exports of LNG to non-FTA countries until DOE can...

Construction advances on Sempra’s Port Arthur LNG export terminal

In March last year, Sempra Infrastructure, a unit of Sempra, took a final investment decision for the first phase of its...