Cheniere says 6th Sabine Pass train produces first LNG

US LNG export firm Cheniere said it has started producing LNG from the sixth production train at its Sabine Pass liquefaction plant in Louisiana.

Cheniere Energy Partners, a unit of Cheniere, revealed this in a statement on Tuesday.

The firm said that the commissioning process continues and it expects substantial completion of the 5 mtpa unit in the first quarter of 2022.

Substantial completion of the liquefaction unit is expected one year ahead of the guaranteed completion date.

In September, Cheniere introduced feed gas to the unit after receiving approval from the Federal Energy Regulatory Commission (FERC).

Bechtel is building this train, such as the previous five units and the three trains at Cheniere’s Corpus Christi plant.

Upon completion, Bechtel would transfer the completed train to Cheniere Partners, and Sabine Pass’ total production capacity would reach about 30 mtpa of LNG, the firm said.

“This milestone is yet another impressive achievement by the Bechtel and Cheniere teams who continue to safely commission and bring our LNG trains online ahead of schedule and within project budgets,” Cheniere’s chief executive Jack Fusco, said.

“With global economic activity increasing and the winter season approaching in key LNG markets around the world, providing additional supplies of reliable LNG can help companies, countries and communities around the world during this high-demand period,” he said.

Most Popular

Cedar FLNG launched in South Korea

South Korea’s Samsung Heavy Industries has launched Cedar LNG's floating LNG production unit, which will be installed in Kitimat on Canada’s West Coast.

India’s Petronet LNG declares force majeure to offtakers

India's largest LNG importer has declared force majeure to its offtakers after it received a notice from state-owned QatarEnergy, which on Monday stopped production at its giant Ras Laffan LNG plant due to attacks.

BP submits lowest bid in Pakistan LNG tender

A unit of UK-based energy giant BP has submitted the lowest bid in a tender to supply Pakistan with one spot LNG shipment this week.

More News Like This

Cheniere, Bechtel seal EPC deal for first Sabine Pass LNG expansion phase

A unit of Cheniere Energy Partners has entered into a lump sum, turnkey, engineering, procurement, and construction (EPC) contract with Bechtel for the first phase of the Sabine Pass LNG expansion project in Louisiana. In addition, Bechtel has received a limited notice to proceed to start early engineering and procurement for the project.

Cheniere reports $3.5 billion net loss, higher revenue in Q1

US LNG exporting giant Cheniere reported a first-quarter net loss of $3.5 ​billion and revenue of $5.87 billion, a rise of 7.8 percent year-on-year.

Corpus Christi Stage 3 project 96.5 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 96.5 percent complete, according to the latest construction update.

Cheniere nears launch of sixth Corpus Christi expansion train

US LNG exporter Cheniere is close to launching the sixth train at the Corpus Christi Stage 3 expansion project in Texas.