Cheniere says third Sabine Pass jetty almost 85 percent complete

US LNG exporting giant Cheniere and compatriot engineer Bechtel are moving forward with works on the third jetty at the six-train 30 mtpa Sabine Pass facility in Louisiana.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year, Cheniere previously said.

Cheniere won approval from FERC to build the jetty in February 2020 and after that issued a notice to proceed to Bechtel.

According to the latest construction update filed with FERC, the project was 84.2 percent complete as of April this year, against the plan of 89.6 percent.

Cheniere said in the update that engineering was 100 percent complete, procurement 93.5 percent, subcontracts 96.6 percent, while construction was 64.2 percent complete.

Launch nearing

During the month of April, construction completed the setting of modules three and four, and finished erecting the stick-built piperack, according to Cheniere.

Following FERC authorization to install aboveground piping and equipment on April 8, 2022, hydrocarbon piping installation has started in the stickbuilt piperack, it said.

In addition, April activities also included the completion of the upper LNG transfer arms.

Cheniere did not reveal in the update when it expects to complete the jetty. In the original schedule, the firm had expected to launch the jetty in the first quarter of 2023.

However, Cheniere said in its May investor presentation that operations of the jetty could start by the end of this year.

High demand from Europe

Cheniere’s Sabine Pass and Corpus Christi plants shipped record number of LNG cargoes in the first quarter this year due to a surge in demand from Europe.

The two terminals exported in total 160 LNG cargoes, compared to 133 cargoes in the first quarter of 2020.

About 75 percent of these cargoes landed in Europe due to high prices and as European countries look to slash reliance on Russian gas.

Most Popular

South Korea’s Posco says first LNG carrier to start ops in H2

Posco International, a unit of South Korean steel producer Posco, plans to start shipping LNG with its first dedicated LNG carrier in the second half of this year.

Canada’s Cedar LNG names FLNG

Canada’s Cedar LNG, a joint venture of Canada’s Pembina Pipeline and the Haisla Nation, has picked a name for its floating LNG facility, which will be located in the traditional territory of the Haisla Nation, on Canada’s West Coast.

Atlantic LNG shipping rates continue to decrease

Atlantic LNG freight shipping rates continued to decrease this week, while European prices also dropped compared to last week.

More News Like This

Cheniere to introduce feed gas to second Corpus Christi expansion train

US LNG exporter Cheniere is nearing the introduction of feed gas to the second train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere, Canadian Natural Resources pen gas supply deal

US LNG exporter Cheniere has signed a long-term deal with Canadian Natural Resources under which the latter will supply natural gas to a unit of Cheniere.

Cheniere gets OK to introduce fuel gas to second Corpus Christi expansion train

US LNG exporter Cheniere has received approval from the US FERC to introduce fuel gas to the second train of the Corpus Christi Stage 3 expansion project in Texas as part of the commissioning phase.

Cheniere nears first LNG at second Corpus Christi expansion train

Cheniere's CEO, Jack Fusco, expects the company to achieve first LNG at the second train of the Corpus Christi Stage 3 expansion project in Texas later this month or at the beginning of June.