Cheniere says third Sabine Pass jetty almost 85 percent complete

US LNG exporting giant Cheniere and compatriot engineer Bechtel are moving forward with works on the third jetty at the six-train 30 mtpa Sabine Pass facility in Louisiana.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year, Cheniere previously said.

Cheniere won approval from FERC to build the jetty in February 2020 and after that issued a notice to proceed to Bechtel.

According to the latest construction update filed with FERC, the project was 84.2 percent complete as of April this year, against the plan of 89.6 percent.

Cheniere said in the update that engineering was 100 percent complete, procurement 93.5 percent, subcontracts 96.6 percent, while construction was 64.2 percent complete.

Launch nearing

During the month of April, construction completed the setting of modules three and four, and finished erecting the stick-built piperack, according to Cheniere.

Following FERC authorization to install aboveground piping and equipment on April 8, 2022, hydrocarbon piping installation has started in the stickbuilt piperack, it said.

In addition, April activities also included the completion of the upper LNG transfer arms.

Cheniere did not reveal in the update when it expects to complete the jetty. In the original schedule, the firm had expected to launch the jetty in the first quarter of 2023.

However, Cheniere said in its May investor presentation that operations of the jetty could start by the end of this year.

High demand from Europe

Cheniere’s Sabine Pass and Corpus Christi plants shipped record number of LNG cargoes in the first quarter this year due to a surge in demand from Europe.

The two terminals exported in total 160 LNG cargoes, compared to 133 cargoes in the first quarter of 2020.

About 75 percent of these cargoes landed in Europe due to high prices and as European countries look to slash reliance on Russian gas.

Most Popular

Energy Transfer seals Lake Charles LNG supply deals

Texas-based Energy Transfer has signed new supply deals for its planned Lake Charles LNG export facility in Louisiana as it works to take a final investment decision by the end of this year, according to its management.

Samsung Heavy develops new FLNG concept

South Korean shipbuilding giant Samsung Heavy Industries has received approvals from three classification societies for its new multi-purpose FLNG concept.

ExxonMobil CEO expects Golden Pass LNG launch by end of this year

ExxonMobil CEO Darren Woods expects the QatarEnergy-led Golden Pass LNG export project in Texas to produce first LNG volumes by the end of this year. Separately, Golden Pass LNG is also seeking approval from the US FERC to increase peak workforce up to 10,300.

More News Like This

Cheniere reports higher Q1 revenue

US LNG exporting giant Cheniere reported a rise in its quarterly revenue due to higher prices, while its net profit decreased compared to the same period last year.

Cheniere to introduce fuel gas to second Corpus Christi LNG expansion train

US LNG exporter Cheniere is nearing the introduction of fuel gas to the second train of the Corpus Christi Stage 3 expansion project in Texas as part of the commissioning phase.

Three dead in accident at Port Arthur LNG site

Sempra Infrastructure and Bechtel confirmed that an incident took place on Tuesday at the Port Arthur LNG construction site in Texas, resulting in three fatalities and two injuries.

Cheniere’s Corpus Christi expansion project 82.5 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 82.5 percent complete.