Cheniere says third Sabine Pass jetty almost 85 percent complete

US LNG exporting giant Cheniere and compatriot engineer Bechtel are moving forward with works on the third jetty at the six-train 30 mtpa Sabine Pass facility in Louisiana.

Cheniere is adding the third marine berth and supporting facilities to boost operating flexibility at the Sabine Pass LNG facility.

The jetty will have the capability to load LNG carriers with a capacity of 125,000-180,000 cubic meters.

It will increase the maximum number of calls by LNG carriers with a capacity of up to 180,000 cbm at the plant by 180 per year, Cheniere previously said.

Cheniere won approval from FERC to build the jetty in February 2020 and after that issued a notice to proceed to Bechtel.

According to the latest construction update filed with FERC, the project was 84.2 percent complete as of April this year, against the plan of 89.6 percent.

Cheniere said in the update that engineering was 100 percent complete, procurement 93.5 percent, subcontracts 96.6 percent, while construction was 64.2 percent complete.

Launch nearing

During the month of April, construction completed the setting of modules three and four, and finished erecting the stick-built piperack, according to Cheniere.

Following FERC authorization to install aboveground piping and equipment on April 8, 2022, hydrocarbon piping installation has started in the stickbuilt piperack, it said.

In addition, April activities also included the completion of the upper LNG transfer arms.

Cheniere did not reveal in the update when it expects to complete the jetty. In the original schedule, the firm had expected to launch the jetty in the first quarter of 2023.

However, Cheniere said in its May investor presentation that operations of the jetty could start by the end of this year.

High demand from Europe

Cheniere’s Sabine Pass and Corpus Christi plants shipped record number of LNG cargoes in the first quarter this year due to a surge in demand from Europe.

The two terminals exported in total 160 LNG cargoes, compared to 133 cargoes in the first quarter of 2020.

About 75 percent of these cargoes landed in Europe due to high prices and as European countries look to slash reliance on Russian gas.

Most Popular

Woodside names Sarah Bairstow as Louisiana LNG head

Australian LNG player Woodside has appointed Sarah Bairstow to lead its Louisiana LNG project.

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

BP, partners ship first Tortue LNG cargo

UK-based energy giant BP and its partners have shipped the first liquefied natural gas (LNG) cargo produced at the Greater Tortue Ahmeyim FLNG project, located offshore Mauritania and Senegal, according to shipping data.

More News Like This

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

Port of Corpus Christi says Q1 LNG volumes up 12.3 percent

The US Port of Corpus Christi in Texas reported a 12.3 percent year-on-year increase in its liquefied natural gas (LNG) volumes in the first quarter of this year.

Cheniere progresses commissioning of second Corpus Christi expansion train

US LNG exporting giant Cheniere is moving forward with commissioning activities at the second train of the Corpus Christi Stage 3 expansion project in Texas following the substantial completion of the first unit.

Corpus Christi LNG expansion project 80 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 80 percent complete.