Cheniere to introduce feed gas to 6th Sabine Pass LNG train

US LNG export firm Cheniere will soon introduce feed gas to the sixth production train at its Sabine Pass liquefaction plant in Louisiana.

The firm’s unit is seeking approval from the Federal Energy Regulatory Commission (FERC), according to a filing dated September 15.

“Sabine Pass is herein requesting authorization to introduce FEED gas and refrigerants in order to continue its commissioning activities for Train 6,” it said.

It is requesting authorization “at the earliest time possible, but no later than September 21, 2021, in order to remain on schedule.”

Cheniere’s chief executive Jack Fusco said in August the firm had started early commissioning activities at the sixth Sabine Pass production train.

Fusco also said that the project had reached 89.6 percent completion as of the end of June.

In addition, Cheniere expects substantial completion at the liquefaction unit in the first quarter of 2022.

The 25 mtpa Sabine Pass plant has five operational trains and is currently the largest such facility in the US.

Bechtel is building the sixth train which will add 5 mtpa of capacity to the facility.

In total, this is the ninth train the engineering giant is building for Cheniere, including the Corpus Christi plant where Bechtel handed over the third train earlier this year.

Most Popular

CoolCo seeks long-term employment for two LNG carriers

In August, Coolco said it plans to employ its first newbuild LNG vessel, Kool Tiger, on a shorter deal...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

Japan’s K Line on track with LNG fleet growth plans

According to K Line's latest financial report, the firm had 46 LNG carriers in its fleet as of the...

More News Like This

Corpus Christi LNG expansion project 73.2 percent complete

Cheniere’s Corpus Christi plant currently liquefies natural gas at three operational trains, each with a capacity of about 5...

Cheniere sets methane emissions target for its LNG terminals

US LNG exporting giant Cheniere said it had set a voluntary, measurement-informed scope 1 annual methane intensity target for...

Cheniere CEO: Corpus Christi expansion project to get first gas in coming weeks

Cheniere’s Corpus Christi plant in Texas currently liquefies natural gas at three operational trains, each with a capacity of...

Cheniere boosts LNG shipments in January-September

The owner of the Sabine Pass and Corpus Christi LNG export terminals said on Thursday that its revenue reached...