Cheniere to introduce feed gas to 6th Sabine Pass LNG train

US LNG export firm Cheniere will soon introduce feed gas to the sixth production train at its Sabine Pass liquefaction plant in Louisiana.

The firm’s unit is seeking approval from the Federal Energy Regulatory Commission (FERC), according to a filing dated September 15.

“Sabine Pass is herein requesting authorization to introduce FEED gas and refrigerants in order to continue its commissioning activities for Train 6,” it said.

It is requesting authorization “at the earliest time possible, but no later than September 21, 2021, in order to remain on schedule.”

Cheniere’s chief executive Jack Fusco said in August the firm had started early commissioning activities at the sixth Sabine Pass production train.

Fusco also said that the project had reached 89.6 percent completion as of the end of June.

In addition, Cheniere expects substantial completion at the liquefaction unit in the first quarter of 2022.

The 25 mtpa Sabine Pass plant has five operational trains and is currently the largest such facility in the US.

Bechtel is building the sixth train which will add 5 mtpa of capacity to the facility.

In total, this is the ninth train the engineering giant is building for Cheniere, including the Corpus Christi plant where Bechtel handed over the third train earlier this year.

Most Popular

BW LNG seals Jordan FSU charter deal

In addition, NEPCO will acquire ownership of the vessel at the end of the charter period, BW LNG said...

South Korea’s HD Hyundai Mipo to build LNG bunkering duo

HD Hyundai Mipo said on Thursday it will deliver these two vessels by November 2027. The vessels will have a...

Geocean completes offshore work on second Wilhelmshaven LNG terminal in Germany

French marine and offshore contractor, Geocean, a unit of VINCI Construction Grands Projets, has completed its contract awarded by...

More News Like This

Cheniere’s Corpus Christi LNG expansion project 64 percent complete

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa. In...

Cheniere expects Asian LNG demand to nearly double by 2040

Cheniere is the largest LNG exporter in the US. The company’s Sabine Pass facility in Louisiana currently has a capacity...

Cheniere’s Corpus Christi seeks approval to place supply line facilities in service

Last year, FERC approved construction of the terminal supply line facilities. These facilities include a pig launcher adjacent to the...

Cheniere ships 3,570 LNG cargoes, expansion plans progressing

Cheniere’s Sabine Pass facility in Louisiana currently has a capacity of about 30 mtpa following the launch of the sixth...