Cheniere to introduce feed gas to 6th Sabine Pass LNG train

US LNG export firm Cheniere will soon introduce feed gas to the sixth production train at its Sabine Pass liquefaction plant in Louisiana.

The firm’s unit is seeking approval from the Federal Energy Regulatory Commission (FERC), according to a filing dated September 15.

“Sabine Pass is herein requesting authorization to introduce FEED gas and refrigerants in order to continue its commissioning activities for Train 6,” it said.

It is requesting authorization “at the earliest time possible, but no later than September 21, 2021, in order to remain on schedule.”

Cheniere’s chief executive Jack Fusco said in August the firm had started early commissioning activities at the sixth Sabine Pass production train.

Fusco also said that the project had reached 89.6 percent completion as of the end of June.

In addition, Cheniere expects substantial completion at the liquefaction unit in the first quarter of 2022.

The 25 mtpa Sabine Pass plant has five operational trains and is currently the largest such facility in the US.

Bechtel is building the sixth train which will add 5 mtpa of capacity to the facility.

In total, this is the ninth train the engineering giant is building for Cheniere, including the Corpus Christi plant where Bechtel handed over the third train earlier this year.

Most Popular

Venture Global withdraws Delta LNG application

US LNG exporter Venture Global LNG is withdrawing its FERC application for the proposed 24.4 mtpa Delta LNG export facility in Louisiana. Instead, Venture Global will focus on expanding its Plaquemines LNG export facility in Louisiana.

Cheniere aims to start construction on Sabine Pass LNG expansion in late 2026

US LNG exporting giant Cheniere aims to start construction on the proposed expansion project at its Sabine Pass LNG export facility in Louisiana in late 2026.

Delfin seeks new DOE extension, eyes FID on first FLNG in August

Delfin Midstream, the US developer of a floating LNG export project offshore Louisiana, is seeking an additional extension from the US Department of Energy. The company is looking to make a final investment decision on the first FLNG in August.

More News Like This

Japan’s Jera seals US LNG supply deals

Japan's power firm and LNG trader Jera has signed 20-year agreements to buy up to 5.5 million tonnes per year of LNG from the United States. The deals include an SPA with Commonwealth LNG and the previously announced SPA with NextDecade, as well as heads of agreements with Sempra Infrastructure and Cheniere.

Cheniere aims to start construction on Sabine Pass LNG expansion in late 2026

US LNG exporting giant Cheniere aims to start construction on the proposed expansion project at its Sabine Pass LNG export facility in Louisiana in late 2026.

Cheniere’s Corpus Christi expansion project almost 84 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 84 percent complete.

Port of Corpus Christi completes ship channel expansion

The US Port of Corpus Christi in Texas has completed the $625 million ship channel improvement project.