Cheniere to introduce feed gas to 6th Sabine Pass LNG train

US LNG export firm Cheniere will soon introduce feed gas to the sixth production train at its Sabine Pass liquefaction plant in Louisiana.

The firm’s unit is seeking approval from the Federal Energy Regulatory Commission (FERC), according to a filing dated September 15.

“Sabine Pass is herein requesting authorization to introduce FEED gas and refrigerants in order to continue its commissioning activities for Train 6,” it said.

It is requesting authorization “at the earliest time possible, but no later than September 21, 2021, in order to remain on schedule.”

Cheniere’s chief executive Jack Fusco said in August the firm had started early commissioning activities at the sixth Sabine Pass production train.

Fusco also said that the project had reached 89.6 percent completion as of the end of June.

In addition, Cheniere expects substantial completion at the liquefaction unit in the first quarter of 2022.

The 25 mtpa Sabine Pass plant has five operational trains and is currently the largest such facility in the US.

Bechtel is building the sixth train which will add 5 mtpa of capacity to the facility.

In total, this is the ninth train the engineering giant is building for Cheniere, including the Corpus Christi plant where Bechtel handed over the third train earlier this year.

Most Popular

Venture Global seeks FERC OK for CP2 LNG expansion

US LNG exporter Venture Global LNG has filed a new application with the US FERC seeking approval to add approximately 11.7 million metric tonnes per annum of capacity at its CP2 LNG project in Louisiana.

Australia’s Woodside denies takeover talks with ExxonMobil

Australian LNG player Woodside said on Monday that it is not in discussions with US energy giant ExxonMobil regarding a potential transaction following media reports.

Yangzijiang charters its first LNG carrier

Chinese private shipyard Yangzijiang Shipbuilding has chartered its first 175,000-cbm liquefied natural gas (LNG) carrier to capitalize on opportunities arising from the volatile market

More News Like This

Cheniere completes sixth train at Corpus Christi expansion project

US LNG exporter Cheniere has reached substantial completion of the sixth liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.

Cheniere, Bechtel seal EPC deal for first Sabine Pass LNG expansion phase

A unit of Cheniere Energy Partners has entered into a lump sum, turnkey, engineering, procurement, and construction (EPC) contract with Bechtel for the first phase of the Sabine Pass LNG expansion project in Louisiana. In addition, Bechtel has received a limited notice to proceed to start early engineering and procurement for the project.

Cheniere reports $3.5 billion net loss, higher revenue in Q1

US LNG exporting giant Cheniere reported a first-quarter net loss of $3.5 ​billion and revenue of $5.87 billion, a rise of 7.8 percent year-on-year.

Corpus Christi Stage 3 project 96.5 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 96.5 percent complete, according to the latest construction update.