Cheniere’s Corpus Christi LNG expansion project almost 50 percent complete

US LNG exporting giant Cheniere and compatriot Bechtel are moving forward with the construction work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the November construction report filed with the US FERC that overall project completion for the Stage 3 project is 48.8 percent.

Stage 3 engineering and procurement are 80 percent and 69 percent complete, respectively, while subcontract and direct hire construction work are 63.1 percent and 9.8 percent complete, respectively, it said.

Cheniere's Corpus Christi LNG expansion project almost 50 percent complete
Train 1 air-cooled heat exchangers (Image: Cheniere)

Work progressing

During November, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in Trains 5 and 6, as well as OSBL phase, the firm said.

Concrete work is progressing in train 2 and OSBL south. Aboveground piping continues to be connected and integrated with pipe spools in the train 1 cryo racks and will continue in the AGRU area in the upcoming weeks, it said.

Key equipment installations include the train 1 cold boxes, utility substation, and hot oil furnace.

In August, first cold boxes arrived at the site.

Last year, US equipment manufacturer Chart Industries received full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s unit said that additional major installations are planned for December 2023, such as the GIS substation and the first refrigeration compressor.

Ahead of schedule

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

Cheniere's Corpus Christi LNG expansion project almost 50 percent complete
East ground flare 1 (Image: Cheniere)

However, Cheniere’s CEO Jack Fusco said in August that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

The expansion project was 44.1 percent complete as of September 30.

Most Popular

YPF, Shell seal Argentina LNG deal

YPF president and CEO Horacio Marin, and Shell's executive VP of LNG, Cederic Cremers,signed the deal in The Hague,...

Brazil’s Eneva launches small liquefaction plant

According to a statement by Eneva on December 17, the small liquefaction unit started commercial operations following commissioning and...

Chevron and Woodside in Australian LNG asset swap deal

The two firms announced the deal in separate statements on Thursday. Under the proposed transaction, Chevron Australia will transfer to...

More News Like This

US DOE releases LNG export study

The Biden administration said in January it will pause pending decisions on exports of LNG to non-FTA countries until DOE can...

Woodside, Bechtel seal revised EPC deal for Louisiana LNG project

Woodside said on Thursday the lump sum turnkey deal is for the three-train 16.5 million tonnes per annum foundation...

Cheniere’s Corpus Christi LNG expansion project to receive first gas

The US FERC said on Wednesday that it had granted Corpus Christi Liquefaction's request to introduce hydrocarbons to Train...

Corpus Christi LNG expansion project 73.2 percent complete

Cheniere’s Corpus Christi plant currently liquefies natural gas at three operational trains, each with a capacity of about 5...