Cheniere’s Corpus Christi LNG expansion project almost 50 percent complete

US LNG exporting giant Cheniere and compatriot Bechtel are moving forward with the construction work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now consists of three operational trains with each having a capacity of about 5 mtpa.

In June last year, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the November construction report filed with the US FERC that overall project completion for the Stage 3 project is 48.8 percent.

Stage 3 engineering and procurement are 80 percent and 69 percent complete, respectively, while subcontract and direct hire construction work are 63.1 percent and 9.8 percent complete, respectively, it said.

Cheniere's Corpus Christi LNG expansion project almost 50 percent complete
Train 1 air-cooled heat exchangers (Image: Cheniere)

Work progressing

During November, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in Trains 5 and 6, as well as OSBL phase, the firm said.

Concrete work is progressing in train 2 and OSBL south. Aboveground piping continues to be connected and integrated with pipe spools in the train 1 cryo racks and will continue in the AGRU area in the upcoming weeks, it said.

Key equipment installations include the train 1 cold boxes, utility substation, and hot oil furnace.

In August, first cold boxes arrived at the site.

Last year, US equipment manufacturer Chart Industries received full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s unit said that additional major installations are planned for December 2023, such as the GIS substation and the first refrigeration compressor.

Ahead of schedule

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

Cheniere's Corpus Christi LNG expansion project almost 50 percent complete
East ground flare 1 (Image: Cheniere)

However, Cheniere’s CEO Jack Fusco said in August that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

The expansion project was 44.1 percent complete as of September 30.

Most Popular

Taiwan’s CPC inks initial Alaska LNG deal

Taiwan’s CPC Corp has signed a letter of intent with Alaska Gasline Development Corporation (AGDC) to buy LNG and invest in the latter's planned Alaska LNG project.

DET terminates Stade FSRU contract with HEH

State-owned German LNG terminal operator DET has terminated the contract related to the Stade FSRU-based facility with compatriot Hanseatic Energy Hub, the developer of the onshore LNG terminal in Stade.

Venture Global’s CP2 LNG project gets non-FTA approval from DOE

US LNG exporter Venture Global LNG has received conditional non-FTA approval from the US Department of Energy for its proposed CP2 LNG project in Louisiana.

More News Like This

Cheniere completes first train at Corpus Christi expansion project

US LNG exporting giant Cheniere has achieved substantial completion of the first liquefaction train at the Corpus Christi Stage 3 expansion project in Texas.

Cheniere gets FERC OK for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere has received approval from the US FERC to build two more midscale trains at its Corpus Christi LNG plant in Texas.

Corpus Christi LNG expansion project 78.3 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 78.3 percent complete.

Cheniere targets Sabine Pass LNG expansion FID in 2026 or 2027

US LNG exporting giant Cheniere plans to make a final investment decision to expand its giant Sabine Pass LNG plant in Louisiana in late 2026 or 2027, according to its management.