Cheniere’s Corpus Christi LNG expansion project more than 51 complete

US LNG exporter Cheniere and compatriot Bechtel have completed more than half of the work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October the same year.

The project was 48.1 percent complete in November last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the December construction report filed with the US FERC this week that overall project completion for the Stage 3 project is 51.4 percent.

Stage 3 engineering and procurement are 83.7 percent and 72.2 percent complete, respectively, while subcontract and direct hire construction work are 66.9 percent and 11.1 percent complete, respectively, it said.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
Train 1 mixed refrigerant compressor set (Image: Cheniere)

First train concrete work “significantly” complete

During December, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in trains 5, 6, and 7, while concrete work in train 1 is “significantly” complete, the firm said.

Concrete pouring is also underway in train 2 and train 3, and loading of aboveground piping spools is progressing in train 1.

Several large pieces of equipment have been installed including train 1 refrigeration compressors, train 1 liquefaction substation, train 2 cold boxes, the GIS substation, and train 2 utility substation, it said.

In August last year, first cold boxes arrived at the site.

US equipment manufacturer Chart Industries received in 2022 full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
OSBL west piperack erection (Image: Cheniere)

First LNG production by end of 2024

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

Most Popular

Venture Global’s Plaquemines LNG terminal achieves first production

Venture Global announced on Friday it had reached first LNG production at the company’s second facility, Plaquemines LNG, in...

Spot LNG rates remain weak

“Spark30S rates rose for a fourth consecutive week, increasing marginally by $750 to $23,500 per day,” Qasim Afghan, Spark’s commercial...

Swan Energy, Nebula’s AG&P LNG plan Indian JV

Swan Energy said on Friday it had signed a heads of agreement with AG&P Terminals &Logistics (Singapore). The two firms...

More News Like This

US DOE releases LNG export study

The Biden administration said in January it will pause pending decisions on exports of LNG to non-FTA countries until DOE can...

Cheniere’s Corpus Christi LNG expansion project to receive first gas

The US FERC said on Wednesday that it had granted Corpus Christi Liquefaction's request to introduce hydrocarbons to Train...

Corpus Christi LNG expansion project 73.2 percent complete

Cheniere’s Corpus Christi plant currently liquefies natural gas at three operational trains, each with a capacity of about 5...

Cheniere sets methane emissions target for its LNG terminals

US LNG exporting giant Cheniere said it had set a voluntary, measurement-informed scope 1 annual methane intensity target for...