Cheniere’s Corpus Christi LNG expansion project more than 51 complete

US LNG exporter Cheniere and compatriot Bechtel have completed more than half of the work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October the same year.

The project was 48.1 percent complete in November last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the December construction report filed with the US FERC this week that overall project completion for the Stage 3 project is 51.4 percent.

Stage 3 engineering and procurement are 83.7 percent and 72.2 percent complete, respectively, while subcontract and direct hire construction work are 66.9 percent and 11.1 percent complete, respectively, it said.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
Train 1 mixed refrigerant compressor set (Image: Cheniere)

First train concrete work “significantly” complete

During December, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in trains 5, 6, and 7, while concrete work in train 1 is “significantly” complete, the firm said.

Concrete pouring is also underway in train 2 and train 3, and loading of aboveground piping spools is progressing in train 1.

Several large pieces of equipment have been installed including train 1 refrigeration compressors, train 1 liquefaction substation, train 2 cold boxes, the GIS substation, and train 2 utility substation, it said.

In August last year, first cold boxes arrived at the site.

US equipment manufacturer Chart Industries received in 2022 full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
OSBL west piperack erection (Image: Cheniere)

First LNG production by end of 2024

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

- Advertisements -

Most Popular

Hyundai Samho to build LNG carrier quartet for $1.08 billion

South Korea's Hyundai Samho has secured an order to build four liquefied natural gas (LNG) carriers for about $1.08...

Tellurian reports $166.2 million net loss in 2023

US LNG firm Tellurian reported a net loss of $166.2 million in 2023, as it continues to work on...

QatarEnergy to further boost LNG output

State-owned LNG giant QatarEnergy said on Sunday it will further boost its liquefied natural gas production from the North...

More News Like This

CEO: DOE’s permit pause will not slow down Cheniere’s LNG expansion plans

US LNG exporting giant Cheniere is going "full steam ahead" with plans to expand its Sabine Pass and Corpus...

Cheniere: 2023 net profit jumps, revenue down

US LNG exporting giant Cheniere reported a 39 percent drop in its 2023 revenue due to lower prices, while...

GasLog, Cheniere extend LNG carrier charter deal

Greek LNG shipping firm GasLog has extended a charter deal for one of its vessels with a unit of...

US LNG exporter Cheniere uplisted to NYSE

US LNG exporting giant Cheniere Energy and Cheniere Energy Partners have each been approved for uplisting to the New...