Cheniere’s Corpus Christi LNG expansion project more than 51 complete

US LNG exporter Cheniere and compatriot Bechtel have completed more than half of the work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October the same year.

The project was 48.1 percent complete in November last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the December construction report filed with the US FERC this week that overall project completion for the Stage 3 project is 51.4 percent.

Stage 3 engineering and procurement are 83.7 percent and 72.2 percent complete, respectively, while subcontract and direct hire construction work are 66.9 percent and 11.1 percent complete, respectively, it said.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
Train 1 mixed refrigerant compressor set (Image: Cheniere)

First train concrete work “significantly” complete

During December, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in trains 5, 6, and 7, while concrete work in train 1 is “significantly” complete, the firm said.

Concrete pouring is also underway in train 2 and train 3, and loading of aboveground piping spools is progressing in train 1.

Several large pieces of equipment have been installed including train 1 refrigeration compressors, train 1 liquefaction substation, train 2 cold boxes, the GIS substation, and train 2 utility substation, it said.

In August last year, first cold boxes arrived at the site.

US equipment manufacturer Chart Industries received in 2022 full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
OSBL west piperack erection (Image: Cheniere)

First LNG production by end of 2024

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

Most Popular

Jera boosts Wheatstone LNG stake

Japan’s power firm and LNG trader, Jera, has strengthened its indirect stake in the Chevron-operated Wheatstone LNG project in Australia by acquiring additional shares.

Taiwan’s CPC makes progress with Alaska LNG deal

Taiwan’s CPC Corp is making progress on buying LNG and investing in the planned Glenfarne-led Alaska LNG project, according to Taiwan's economy ministry.

Shell, GTT, and LR to develop new LNG carrier

UK-based LNG giant Shell, French LNG containment specialist GTT, and classification society Lloyd’s Register have launched a joint development project to develop a conceptual 200,000-cbm LNG carrier combining hybrid-electric propulsion with GTT’s Next1 LNG cargo containment technology.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

Cheniere, Petrobras seal long-term LNG SPA

US LNG exporter Cheniere has signed a long-term LNG sale and purchase agreement with Brazil’s state-owned energy firm Petrobras

US FERC issues final EIS for Cheniere’s Sabine Pass expansion project

The US Federal Energy Regulatory Commission (FERC) has released a final environmental impact statement for Cheniere’s planned Sabine Pass Stage 5 expansion project. The regulator confirmed that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”

FERC issues draft EIS for Cheniere’s Corpus Christi Stage 4 project

The US Federal Energy Regulatory Commission (FERC) has released a draft environmental impact statement for Cheniere’s planned Corpus Christi Liquefaction Stage IV expansion project in Texas. The regulator concluded that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”