Cheniere’s Corpus Christi LNG expansion project more than 51 complete

US LNG exporter Cheniere and compatriot Bechtel have completed more than half of the work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October the same year.

The project was 48.1 percent complete in November last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the December construction report filed with the US FERC this week that overall project completion for the Stage 3 project is 51.4 percent.

Stage 3 engineering and procurement are 83.7 percent and 72.2 percent complete, respectively, while subcontract and direct hire construction work are 66.9 percent and 11.1 percent complete, respectively, it said.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
Train 1 mixed refrigerant compressor set (Image: Cheniere)

First train concrete work “significantly” complete

During December, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in trains 5, 6, and 7, while concrete work in train 1 is “significantly” complete, the firm said.

Concrete pouring is also underway in train 2 and train 3, and loading of aboveground piping spools is progressing in train 1.

Several large pieces of equipment have been installed including train 1 refrigeration compressors, train 1 liquefaction substation, train 2 cold boxes, the GIS substation, and train 2 utility substation, it said.

In August last year, first cold boxes arrived at the site.

US equipment manufacturer Chart Industries received in 2022 full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
OSBL west piperack erection (Image: Cheniere)

First LNG production by end of 2024

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

Most Popular

Seapeak to sell three steam LNG carriers

Stonepeak’s Seapeak has initiated the process of selling three steam turbine RasGas II JV liquefied natural gas (LNG) carriers following the expiration of their existing Qatari charter contracts between late 2026 and early 2027.

TotalEnergies, TES launch FEED for US e-methane project

TotalEnergies, TES, and Japanese firms Osaka Gas, Toho Gas, and Itochu have launched front-end engineering design (FEED) activities for the planned Live Oak large-scale facility to produce electric natural gas (e-NG), also known as e-methane, in Nebraska, United States.

Atlantic spot LNG rates drop to $11,750 per day

Atlantic spot LNG shipping rates continued their downward trend this week, dropping to $11,750 per day, according to Spark Commodities.

More News Like This

Cheniere’s net income climbs to $3.07 billion in Q2

US LNG exporting giant Cheniere reported an 88.7 percent year-on-year increase in its second-quarter net income to $3.07 billion, while quarterly revenue rose 23 percent year-on-year to $5.73 billion.

Cheniere set to start LNG production at seventh Corpus Christi expansion train

US LNG exporter Cheniere is set to start LNG production at the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas following the latest approval from the US FERC.

Cheniere gets OK to introduce feed gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere has won approval from the US FERC to introduce feed gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.

Cheniere nears launch of seventh Corpus Christi expansion train

US LNG exporter Cheniere is close to launching the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.