Cheniere’s Corpus Christi LNG expansion project more than 51 complete

US LNG exporter Cheniere and compatriot Bechtel have completed more than half of the work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October the same year.

The project was 48.1 percent complete in November last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the December construction report filed with the US FERC this week that overall project completion for the Stage 3 project is 51.4 percent.

Stage 3 engineering and procurement are 83.7 percent and 72.2 percent complete, respectively, while subcontract and direct hire construction work are 66.9 percent and 11.1 percent complete, respectively, it said.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
Train 1 mixed refrigerant compressor set (Image: Cheniere)

First train concrete work “significantly” complete

During December, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in trains 5, 6, and 7, while concrete work in train 1 is “significantly” complete, the firm said.

Concrete pouring is also underway in train 2 and train 3, and loading of aboveground piping spools is progressing in train 1.

Several large pieces of equipment have been installed including train 1 refrigeration compressors, train 1 liquefaction substation, train 2 cold boxes, the GIS substation, and train 2 utility substation, it said.

In August last year, first cold boxes arrived at the site.

US equipment manufacturer Chart Industries received in 2022 full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
OSBL west piperack erection (Image: Cheniere)

First LNG production by end of 2024

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

Most Popular

Top 5 news of the week July 6-12

LNG Prime brings you the five most popular news stories on our platform during the week of July 6-12, 2026.

Shell, Focol take FID on Bahamas LNG terminal

UK-based LNG giant Shell and its partner Freeport Oil Company (Focol) have taken a final investment decision on a small-scale LNG regasification terminal in the Bahamas.

Singapore LNG, Jiaxing Gas seal LNG terminal use deal

State-owned LNG terminal operator Singapore LNG has signed a terminal use agreement with a unit of Chinese utility Jiaxing Gas.
spot_img

More News Like This

Port of Corpus Christi says H1 LNG volumes up 36 percent

The US Port of Corpus Christi in Texas reported a 36.3 percent year-on-year increase in its liquefied natural gas (LNG) volumes in the second quarter of this year.

Cheniere adds new board member

US LNG exporting giant Cheniere has appointed Britt Vitalone to serve as a member of its board of directors.

Baker Hughes scores equipment and services contracts for Cheniere’s Sabine Pass LNG terminal

US energy services firm Baker Hughes said it had secured three "substantial" awards for Cheniere’s Sabine Pass LNG export facility in Cameron Parish, Louisiana.

Cheniere to introduce fuel gas to seventh Corpus Christi expansion train

US LNG exporter Cheniere is working to introduce fuel gas to the seventh and final train of the Corpus Christi Stage 3 expansion project in Texas.