Cheniere’s Corpus Christi LNG expansion project more than 51 complete

US LNG exporter Cheniere and compatriot Bechtel have completed more than half of the work on the expansion phase at the Corpus Christi LNG export plant in Texas.

Cheniere’s Corpus Christi liquefaction plant now has three operational trains with each having a capacity of about 5 mtpa.

In June 2022, Cheniere took a final investment decision on the Corpus Christi Stage 3 expansion project worth about $8 billion and Bechtel officially started construction on the project in October the same year.

The project was 48.1 percent complete in November last year.

It includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit Corpus Christi Liquefaction said in the December construction report filed with the US FERC this week that overall project completion for the Stage 3 project is 51.4 percent.

Stage 3 engineering and procurement are 83.7 percent and 72.2 percent complete, respectively, while subcontract and direct hire construction work are 66.9 percent and 11.1 percent complete, respectively, it said.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
Train 1 mixed refrigerant compressor set (Image: Cheniere)

First train concrete work “significantly” complete

During December, CCL’s contractor Bechtel continued piling activities, road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel.

Piling and soil stabilization teams are making progress in trains 5, 6, and 7, while concrete work in train 1 is “significantly” complete, the firm said.

Concrete pouring is also underway in train 2 and train 3, and loading of aboveground piping spools is progressing in train 1.

Several large pieces of equipment have been installed including train 1 refrigeration compressors, train 1 liquefaction substation, train 2 cold boxes, the GIS substation, and train 2 utility substation, it said.

In August last year, first cold boxes arrived at the site.

US equipment manufacturer Chart Industries received in 2022 full notice to proceed for the expansion project from Bechtel for its IPMSR process and equipment activities.

Cheniere’s Corpus Christi LNG expansion project more than 51 complete
OSBL west piperack erection (Image: Cheniere)

First LNG production by end of 2024

Cheniere previously said that LNG deliveries from the expansion project will begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

He said in November that construction on Corpus Christi Stage 3 “continues to progress ahead of plan, and I am optimistic first LNG production from train 1 will occur by the end of 2024.”

Most Popular

Technip Energies wins contract for Eni’s Coral Norte FLNG

France-based LNG engineering giant Technip Energies has won a contract for preliminary work on Eni's second FLNG project in Mozambique, Coral Norte (Coral North).

Victrol: LNG London hits bunkering milestone

The Shell-chartered inland bunkering vessel LNG London, owned by a joint venture of Belgium's Victrol and France's Sogestran, has reached a new operational milestone.

Himalaya’s LNG-fueled bulkers earned $34,500 per day in June

LNG-powered bulker owner Himalaya Shipping achieved average time charter equivalent earnings of about $34,500 per day in June.

More News Like This

Cheniere’s Sabine Pass terminal ships 3,000th LNG cargo

Cheniere’s giant Sabine Pass LNG terminal in Louisiana has shipped the 3,000th cargo of liquefied natural gas since its launch in 2016.

Cheniere’s Corpus Christi expansion project 85.4 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 85.4 percent complete.

Cheniere plans to boost LNG export capacity to 100 mtpa

US LNG exporting giant Cheniere plans to boost its export capacity to about 100 mtpa via new expansion projects at its Sabine Pass and Corpus Christi LNG terminals.

Cheniere takes FID on two more Corpus Christi LNG trains

US LNG exporting giant Cheniere has made a positive final investment decision to build two more midscale trains at its Corpus Christi LNG plant in Texas. The company has also issued full notice to proceed to Bechtel.