Delfin seeks more time to build its US floating LNG export project

Delfin LNG, a unit of Delfin Midstream and the developer of a floating LNG export project in the Gulf of Mexico, has requested more time from US FERC to put into service the project’s onshore facilities in Louisiana.

The firm revealed this in a letter to US FERC seeking an additional one-year extension to construct, operate and maintain certain onshore metering, compression, and piping facilities until September 2023.

The facilities would transport and deliver natural gas to Delfin’s deepwater port in federal waters offshore Louisiana.

Delfin plans to install up to four self-propelled FLNG vessels that could produce up to 13 mtpa of LNG or 1.7 billion cubic feet per day of natural gas.

This is the fourth time Delfin has asked FERC for an extension to build the facilities.

However, this request follows a $3 billion long-term deal to supply liquefied natural gas to a unit of energy trader Vitol.

Under the SPA, Delfin will supply 0.5 million tonnes per annum on a free on-board (FOB) basis at its deepwater port to Vitol for a 15-year period.

In addition to the SPA, Vitol has completed a strategic investment in the company.

Delfin seeks more time to build its US floating LNG export project
Image: Delfin LNG

Besides the Vitol deal, Delfin has entered into term sheets or heads of agreement with other LNG off-takers.

The firm told FERC it expects to finalize these deals “soon”.

In addition to this commercial progress, Delfin has completed FEED with Samsung Heavy Industries and Black & Veatch for the construction of the units. The firm has recently
conducted meetings with MARAD, and the US Coast Guard, concerning compliance with the
conditions of its deepwater port authorization as well.

As a modular project consisting of four separate floating LNG vessels, Delfin requires only 2 to 2.5 mtpa of long-term off-take contracts to support a final investment decision and begin construction of its project.

“Given all this significant progress, Delfin LNG is on schedule to make FID on its first FLNGV by the end of this year,” it said.

Most Popular

NextDecade takes FID on fourth Rio Grande LNG train

US LNG firm NextDecade has made a final investment decision on the fourth train at its Rio Grande LNG facility in Texas.

Shell pens US LNG supply deal with Edison

UK-based LNG giant Shell has signed a long-term deal to supply US LNG to Italian energy firm Edison, a unit of EDF.

YPF CEO expects FIDs on FLNG projects with Eni, Shell in 2026

YPF CEO Horacio Marin confirmed on Wednesday that the state-owned oil and gas company and its partners Eni and Shell expect to take final investment decisions on two stages of the Argentina LNG project in 2026.

More News Like This

Golden Pass gets OK to place MP 33 compressor station in service

Golden Pass LNG, a joint venture owned by energy giants QatarEnergy and ExxonMobil, has secured approval from the US FERC to place into service its MP 33 compressor station, as it continues to move forward with commissioning activities at its three-train LNG plant in Texas.

Cheniere’s Corpus Christi expansion project almost 88 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 88 percent complete, while Cheniere has also started site preparation activities for two more midscale trains.

NextDecade’s Rio Grande LNG secures final FERC approval

The US Federal Energy Regulatory Commission (FERC) has issued its final order for NextDecade's Rio Grande LNG facility and the accompanying pipeline in Texas.

Sempra seeks OK to start construction activities for Port Arthur LNG expansion

US LNG exporter Sempra is seeking approval from the Federal Energy Regulatory Commission to start some construction activities for the second phase of the Port Arthur LNG project in Texas, as it continues to work on a final investment decision on the project.