Energy Transfer seeks more time to build Lake Charles LNG export plant

Energy Transfer asked US energy regulators for a three-year extension to construct its proposed Lake Charles LNG export facility in Louisiana.

The Lake Charles LNG project seeks to convert Energy Transfer’s existing regasification terminal to an LNG export facility.

It has a proposed liquefaction capacity of 16.45 million tonnes per year and includes three trains and modifications to the Trunkline Gas pipeline.

LNG giant Shell announced a decision to pull out of the project back in 2020.

Following the Shell decision, Energy Transfer said it would evaluate various alternatives to advance the LNG project including bringing new partners and reducing the plant’s size.

Energy Transfer seeks more time to build Lake Charles LNG export plant
Image: Energy Transfer

In 2019, the company has sought and won an approval from the US FERC for a five-year extension to build the LNG terminal until December 2025.

Now, its units developing the LNG export facility and the pipeline are seeking to extend that deadline until 2028, according to a filling with the FERC dated February 3.

“The applicants state that global market conditions have impacted its ability to reach a final investment decision and secure long-term offtake contracts, thus they now request an additional three years, until December 16, 2028, to complete construction of the project and place it into service,” they said.

Most Popular

First Nations invest in LNG Canada pipeline

Canada's TC Energy, operator of the LNG Canada pipeline, said it had closed an agreement with FN CGL Pipeline, an Indigenous-led investment entity representing five First Nations along the Coastal GasLink corridor.

Germany’s HEH offers additional Stade LNG long-term capacity

Germany’s Hanseatic Energy Hub will offer additional long-term capacity to the market at its land-based liquefied natural gas (LNG) terminal in Stade.

PetroChina delivers first LNG cargo to Gate under long-term capacity deal

PetroChina International, a unit of state-owned PetroChina, has delivered its first LNG cargo to the Dutch Gate LNG import terminal in Rotterdam, owned by Gasunie and Vopak, under a long-term capacity deal.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project 55.6 percent complete

US LNG exporter Cheniere continues to progress construction on its Corpus Christi Midscale Trains 8 and 9 project in Texas.

Venture Global seeks FERC OK to place first Plaquemines LNG phase in service

Venture Global's Plaquemines LNG is seeking approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

NextDecade’s Rio Grande LNG gets FERC OK to boost capacity

US LNG developer NextDecade has secured a green light from the Federal Energy Regulatory Commission to increase approved capacity at its Rio Grande LNG terminal in the Port of Brownsville, Texas.

US FERC issues final EIS for Cheniere’s Sabine Pass expansion project

The US Federal Energy Regulatory Commission (FERC) has released a final environmental impact statement for Cheniere’s planned Sabine Pass Stage 5 expansion project. The regulator confirmed that construction and operation of the LNG project would result in “some adverse environmental effects; however, effects would be reduced to less-than-significant levels.”