Freeport LNG gets OK to start introducing gas into third train

Freeport LNG has secured approval from the US FERC to start introducing natural gas into the third liquefaction train at its three-train 15 mtpa liquefaction plant in Texas as part of the restart process.

According to a filling dated February 1, the FERC granted Freeport LNG’s request to “start commissioning, including cooldown, of the LNG rundown piping system and LNG train 3 (Unit 13).”

In addition, Freeport LNG received approval to “modify the Loop 1 and Dock 1 Cooldown Procedure,” the filling said.

The LNG terminal operator will need to secure additional authorization to “reinstate service for Loop 1 LNG circulation to enable ship loading to Dock 1 and to reinstate service of the liquefaction trains, including rundown piping to tanks.”

Freeport LNG must also comply with any applicable PHMSA and US Coast Guard requirements, the filling said.

The terminal in Texas has been offline for some seven months due to an incident that took place on June 8 last year.

Freeport LNG asked FERC on January 30 to start introducing natural gas into the third liquefaction train.

The company recently won approval from FERC to start introducing LNG into the piping system at the plant.

BP, Jera, Osaka Gas, SK E&S, as well as TotalEnergies have long-term contracts with Freeport LNG.

Most Popular

Venture Global’s Plaquemines LNG terminal achieves first production

Venture Global announced on Friday it had reached first LNG production at the company’s second facility, Plaquemines LNG, in...

Spot LNG rates remain weak

“Spark30S rates rose for a fourth consecutive week, increasing marginally by $750 to $23,500 per day,” Qasim Afghan, Spark’s commercial...

Swan Energy, Nebula’s AG&P LNG plan Indian JV

Swan Energy said on Friday it had signed a heads of agreement with AG&P Terminals &Logistics (Singapore). The two firms...

More News Like This

US DOE releases LNG export study

The Biden administration said in January it will pause pending decisions on exports of LNG to non-FTA countries until DOE can...

Construction advances on Sempra’s Port Arthur LNG export terminal

In March last year, Sempra Infrastructure, a unit of Sempra, took a final investment decision for the first phase of its...

US FERC to prepare supplemental EIS for Venture Global’s CP2 LNG project

In July last year, the regulator issued a final environmental impact statement for the CP2 LNG project, Venture Global’s third LNG...

Cheniere’s Corpus Christi LNG expansion project to receive first gas

The US FERC said on Wednesday that it had granted Corpus Christi Liquefaction's request to introduce hydrocarbons to Train...