Freeport LNG gets OK to start introducing gas into third train

Freeport LNG has secured approval from the US FERC to start introducing natural gas into the third liquefaction train at its three-train 15 mtpa liquefaction plant in Texas as part of the restart process.

According to a filling dated February 1, the FERC granted Freeport LNG’s request to “start commissioning, including cooldown, of the LNG rundown piping system and LNG train 3 (Unit 13).”

In addition, Freeport LNG received approval to “modify the Loop 1 and Dock 1 Cooldown Procedure,” the filling said.

The LNG terminal operator will need to secure additional authorization to “reinstate service for Loop 1 LNG circulation to enable ship loading to Dock 1 and to reinstate service of the liquefaction trains, including rundown piping to tanks.”

Freeport LNG must also comply with any applicable PHMSA and US Coast Guard requirements, the filling said.

The terminal in Texas has been offline for some seven months due to an incident that took place on June 8 last year.

Freeport LNG asked FERC on January 30 to start introducing natural gas into the third liquefaction train.

The company recently won approval from FERC to start introducing LNG into the piping system at the plant.

BP, Jera, Osaka Gas, SK E&S, as well as TotalEnergies have long-term contracts with Freeport LNG.

Most Popular

Japan’s K Line on track with LNG fleet growth plans

According to K Line's latest financial report, the firm had 46 LNG carriers in its fleet as of the...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

Tellurian’s unit seeks more time to build two gas pipelines

Last month, Australia's Woodside acquired all issued and outstanding Tellurian common stock for about $900 million cash, or $1.00 per...

More News Like This

Venture Global moving forward with Plaquemines LNG commissioning

The regulator said in a filing dated November 6 that it grated Venture Global Plaquemines LNG's request to commission...

Golden Pass secures three-year extension to complete Texas LNG terminal

Under the original FERC order from 2016, Golden Pass LNG was required to complete and place into service the...

Cheniere’s Corpus Christi expansion project nears launch of LNG production

"Together with Bechtel, we continue to advance our Corpus Christi Stage 3 project ahead of schedule and anticipate achieving...

Venture Global’s Plaquemines LNG to commission fourth liquefaction block with nitrogen

According to a filing, the regulator approved the commissioning of the block on October 16. The FERC granted the commissioning...