Freeport LNG says to restart first train this week

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, expects to restart the first train this week after the terminal’s fin fan air coolers were damaged during Hurricane Beryl.

The LNG terminal operator ramped down production at its liquefaction end export facility on Sunday, July 7, ahead of Hurricane Beryl making landfall.

“We are safely progressing our efforts towards the phased restart of our liquefaction operations,” a Freeport LNG spokeswoman told LNG Prime on Monday.

She said that Freeport LNG is “completing initial repairs on the damage sustained to our fin fan air coolers in the hurricane and anticipate restarting the first train this week”.

Freeport LNG plans to restart the remaining two trains “shortly thereafter”.

Moreover, the spokeswoman said production levels after restart would be at “reduced rates for a period of time” as Freeport LNG continues repairs while operating the facility.

“Production will steadily ramp up to full rates as these repairs are completed,” she added.

Capacity boost

In May, Freeport LNG resumed operations at all of its three liquefaction trains.

Prior to that, the LNG terminal operator said on March 20 that only the third liquefaction train was operating.

Freeport LNG also used the outage to accelerate a debottlenecking project that will result in the installation of additional compressor capacity across the facility’s three liquefaction unit trains.

The debottlenecking project will increase Freeport LNG’s production capacity from an excess of 15 mtpa to just over 16.5 mtpa.

Freeport LNG’s spokeswoman previously said that the LNG terminal operator has completed the “vast majority of the work related to our debottlenecking project and are working to implement the benefits of those efforts”.

Besides the debottlenecking project, Freeport LNG’s planned train 4, which has received all regulatory approvals, would add an additional 25 percent LNG production capacity.

Of the 15 mtpa of Freeport LNG’s export capacity, 13.4 mtpa has been sold to Osaka Gas, Jera, BP, TotalEnergies, and SK E&S.

Most Popular

Indonesia’s AKRA forms FSRU JV with BW

Indonesian petroleum and chemicals logistics company AKR Corporindo (AKRA) has formed a joint venture with a unit of Singapore-based gas shipping giant BW to develop an FSRU-based LNG project in Indonesia.

Cheniere’s Corpus Christi Stage 3 project 98 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is 98 percent complete, as it continues to progress ahead of schedule, according to the latest construction update.

Inpex buys 85 percent stake in Malaysian block from TotalEnergies

Japan's energy firm and LNG operator Inpex has acquired an 85 percent interest in Block 2E offshore Malaysia from French energy giant TotalEnergies.

More News Like This

Atlantic LNG shipping rates slightly up, Pacific rates down

Atlantic spot LNG shipping rates increased slightly this week, while Pacific rates dropped compared to the week before, according to Spark Commodities.

US LNG exports reach 36 shipments

US liquefied natural gas (LNG) plants sent 36 cargoes during the week ending July 1, up one cargo from the week before, according to the Energy Information Administration.

Atlantic and Pacific LNG shipping rates continue to drop

Atlantic and Pacific liquefied natural gas (LNG) shipping rates continued to decrease this week, according to Spark Commodities.

Egypt was top destination for US LNG cargoes in April

LNG import terminals in Egypt and the Netherlands were the top destinations for US liquefied natural gas cargoes in April this year, according to the Department of Energy’s LNG monthly report.