Glenfarne’s Texas LNG picks Baker Hughes tech, delays FID to 2024

Glenfarne Group’s Texas LNG has selected Baker Hughes to supply gas compression technology equipment, including electric motor drives, for its planned 4 mtpa LNG export terminal.

As part of the partnership between Texas LNG and Baker Hughes, the latter also has a framework agreement to make a strategic pre-FID investment in the project’s late-stage development, according to a statement by Texas LNG issued on Thursday.

The agreement with Baker Hughes facilitates Texas LNG’s “green by design” approach, which intends to use abundant sources of locally procured renewable energy to power the facility and drive the plant’s electric motors, the LNG terminal developer said.

This “green-ready” infrastructure allows Texas LNG to eliminate most CO2 emissions to less than half of a typical LNG export project, making it one of the “lowest-emitting liquefaction facilities in the world,” it said.

FID moved to 2024

Texas LNG said in April that it expects to take a final investment decision to build its LNG export project this year following an order by the US FERC.

FERC issued an order on remand to the planned export terminal in the Port of Brownsville, Texas, owned by Glenfarne Energy Transition’s Texas LNG, following the completion of an additional social cost of carbon and environmental justice analysis.

Last year, the firm said it expected to take FID to build the facility in 2022 and to start commercial operations in 2026.

The developer of the plant also appointed a joint venture of Technip Energies USA and Samsung Engineering to lead the delivery of the facility.

“Texas LNG will close its project financing in 2024 with construction commencing shortly thereafter,” the firm said on Thursday.

Texas LNG said the equipment order is expected to be granted in conjunction with financial close of the project.

The first LNG exports from Texas LNG are expected to be shipped in late 2027 or early 2028, it said.

Most Popular

Woodside issues Louisiana LNG construction update

In October 2024, Woodside acquired all issued and outstanding Tellurian common stock for about $900 million cash, or $1.00 per share....

Trump lifts pause on non-FTA LNG export approvals

Trump issued the executive order, which was widely expected, just hours after officially taking over his second four-year term...

Hoegh Evi, SEFE ink hydrogen pact

Norwegian FSRU player Hoegh Evi, previously known as Hoegh LNG, is joining forces with German gas importer Securing Energy...

More News Like This

Glenfarne confirms Alaska LNG move

"Glenfarne confirms it has entered into an exclusive agreement with AGDC for the development of the Alaska LNG project,...

Baker Hughes bags contract for Woodside’s Louisiana LNG project

Baker Hughes will supply equipment for two liquefaction plants with a total capacity of about 11 mtpa. The order marks...

Glenfarne’s Texas LNG picks Kiewit as EPC contractor

Texas LNG said in a statement it will work with Kiewit to "promptly" complete the pre-final investment decision (FID)...

Baker Hughes expects pace of LNG FIDs to pick up in 2025, CEO says

Baker Hughes booked a record $5.6 billion of LNG equipment orders in 2023 and $3.5 billion in 2022. The company booked only $700...