LNG Canada pipeline 69 percent complete

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, is moving forward with the construction of the pipeline in British Columbia in order to complete it in 2023.

Coastal GasLink said in a update the overall progress had reached 69 percent as of the end of July, compared to about 64.2 percent in the prior month.

“With our workforce at peak numbers, July marked an exciting month as the Wilde Lake compressor station surpassed 90 percent overall completion, and Coastal GasLink is nearing 70 percent overall construction completion,” it said.

“Hydrotesting was a focus for crews at Wilde Lake, and Sections 1 and 2. Significant progress has been made this month to advance construction on Cable Crane Hill in the Coast Mountains and access to the Headwall in the Rocky Mountains,” Coastal GasLink said.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

TC Energy expects to reach mechanical in-service by the end of 2023.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the 14 mtpa LNG Canada facility in Kitimat.

The giant LNG Canada project is now more than 60 percent complete.

Besides Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation and South Korea’s Kogas.

Most Popular

Vopak moving forward with permitting process for Australian LNG import project

Dutch independent storage tank firm Vopak is moving forward with the permitting process for its planned FSRU-based LNG import facility in Australia’s Victoria state, according to CEO Dick Richelle.

Excelerate seals Bahamas LNG deal

US FSRU player Excelerate has signed an 11-year LNG supply agreement with AxDo, a joint venture between Axpo and Bahamas-based energy and maritime logistics company Domicisle LNG, supporting development of the Bahamas LNG hub.

Worley clinches EPC gig for Venture Global’s CP2 LNG expansion project

Australian engineering firm Worley has signed a reimbursable engineering, procurement, and construction (EPC) contract for Venture Global’s CP2 LNG expansion project in Louisiana.

More News Like This

Yokogawa bags LNG Canada Phase 2 gig

A unit of Japanese engineering firm Yokogawa has secured a contract from a joint venture of US engineer Fluor and Japan’s JGC to serve as the main automation contractor for the Shell-led LNG Canada Phase 2 project in Kitimat, British Columbia.

Blackstone-led group buys LNG Canada stake from Mitsubishi

A group led by US-based private equity firm Blackstone has agreed to invest $3.1 billion to acquire a 49.9 percent non-controlling interest in a Mitsubishi subsidiary that holds an interest in the Shell-led LNG Canada project.

Japan’s Kyushu Electric inks LNG Canada deal

Japan’s Kyushu Electric Power has signed a basic agreement with Diamond Global Energy, a unit of Mitsubishi, to buy liquefied natural gas (LNG) from the second phase of the Shell-led LNG Canada project in Kitimat.

Canada backs Fort Simpson LNG power plant

The government of Canada is backing the construction of NTPC's new power plant in Fort Simpson that will primarily generate power using liquefied natural gas (LNG).