LNG Canada pipeline achieves 100 percent pipe installation

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 100 percent pipe installation across the entire project route.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the “final ‘Golden Weld’ took place at the base of Cable Crane Hill in Section 8 West earlier this month.”

This milestone means that all 670 kilometers of pipe has been welded, coated, lowered into the trench, rigorously tested, and backfilled, it said.

“From the Wilde Lake compressor station near Dawson Creek to our metering station in Kitimat, physical construction on the project is now complete,” it said.

“The work is the last step before mechanical completion which is well on track for our year-end target and advances Coastal GasLink as Canada’s first direct path for LNG to international markets,” the firm said.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

Woodside names Sarah Bairstow as Louisiana LNG head

Australian LNG player Woodside has appointed Sarah Bairstow to lead its Louisiana LNG project.

LNG shipping rates continue to decrease

Spot LNG freight shipping rates in both basins continued to decrease this week, while European prices increased compared to last week.

More News Like This

Chris Cooper takes over as LNG Canada CEO

Chris Cooper has taken over as president and chief executive officer of LNG Canada as the Shell-led JV prepares to ship the first LNG cargoes from the Kitimat facility.

Update: Shell’s LNG Canada receives LNG cargo

Shell’s LNG Canada has received a cargo of liquefied natural gas as part of the commissioning and start-up phase.

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.

Shell’s LNG Canada moving forward with commissioning activities

Shell’s LNG Canada is moving forward with its commissioning and start-up phase and expects to receive a liquefied natural gas (LNG) cargo soon.