LNG Canada pipeline achieves 100 percent pipe installation

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 100 percent pipe installation across the entire project route.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the “final ‘Golden Weld’ took place at the base of Cable Crane Hill in Section 8 West earlier this month.”

This milestone means that all 670 kilometers of pipe has been welded, coated, lowered into the trench, rigorously tested, and backfilled, it said.

“From the Wilde Lake compressor station near Dawson Creek to our metering station in Kitimat, physical construction on the project is now complete,” it said.

“The work is the last step before mechanical completion which is well on track for our year-end target and advances Coastal GasLink as Canada’s first direct path for LNG to international markets,” the firm said.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Venture Global seals new deals to support expansion of its power network

US LNG exporter Venture Global has entered into power and grid frame agreements with GE Vernova and Baker Hughes for up to 16 new, 720 MW power island units and associated power transformer equipment, supporting the continued expansion of its existing behind-the-meter, industrial power network that is not reliant on the grid.

Venture Global gets approval to place first Plaquemines LNG phase in service

Venture Global’s Plaquemines LNG has secured approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

MISC orders five more LNG carriers in China

Malaysian shipping firm MISC has officially signed a shipbuilding deal with China’s Hudong-Zhonghua for five additional newbuild 174,000-cbm liquefied natural gas (LNG) carriers, which will serve a 20-year charter with a unit of MISC’s parent, Petronas.

More News Like This

First Nations invest in LNG Canada pipeline

Canada's TC Energy, operator of the LNG Canada pipeline, said it had closed an agreement with FN CGL Pipeline, an Indigenous-led investment entity representing five First Nations along the Coastal GasLink corridor.

Shell, partners take FID on LNG Canada Phase 2

UK-based LNG giant Shell and its LNG Canada partners have made a final investment decision on the project's second phase, which will double production capacity at the facility in Kitimat, British Columbia.

Shell CEO: LNG Canada Phase 2 FID likely by end of this year

Shell CEO Wael Sawan confirmed on Thursday that the company and its LNG Canada partners expect to take a final investment decision on the second phase of the project by the end of this year.

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.