LNG Canada pipeline achieves 90 percent completion

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, has achieved 90 percent overall completion.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in a construction update it still expects to complete the pipeline by the end of 2023.

Section 6, which stretches 63 kilometers from south of Burns Lake to south of Houston, achieved 100 percent pipe installation in June, marking the third of eight sections to complete pipe installation, following Sections 1 and 4 which achieved this milestone last year.

Coastal GasLink said it has completed mainline welding in Section 7, marking the final component of mainline welding across the project, while Section 5 has also completed all pipe installation with the exception of one remaining water crossing.

To date, 625 kilometers of pipe has been installed and nearly 97.5 percent of all pipe has been welded.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

Image: LNG Canada

As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is more than 80 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Woodside updates on Louisiana LNG construction work

Australian LNG producer Woodside has released the latest construction update for the first phase of its Louisiana LNG project.

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.

Atlantic LNG shipping rates rise to $31,000 per day

Atlantic LNG freight rates rose to $31,000 per day this week, while European prices also increased compared to the prior week.

More News Like This

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.

Shell’s LNG Canada moving forward with commissioning activities

Shell’s LNG Canada is moving forward with its commissioning and start-up phase and expects to receive a liquefied natural gas (LNG) cargo soon.

Shell still expects mid-year launch for LNG Canada

Shell's finance chief, Sinead Gorman, told analysts during Shell's fourth-quarter earnings call on Thursday that LNG Canada is making...

Shell’s LNG Canada names new CEO

Cooper, currently LNG Canada’s senior vice president for Phase 1 pipeline and expansion will succeed Jason Klein as president...