LNG Canada pipeline almost 92 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 92 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in a construction update the pipeline has achieved 91.4 percent overall completion and it still expects to complete the project by the end of 2023.

“Our workforce of nearly 4,800 are focused on safely completing remaining critical items across the 670-kilometre project route this summer, while ensuring important environmental management measures are in place,” it said.

“With more than 630 km of pipe installed, crews are busy completing distinct work fronts such as water crossings and steep slopes. To date, more than 92 percent of all classified water crossings are complete, and steep slope areas such as Cable Crane Hill and the Raised Bore, continue to make significant strides forward,” Coastal GasLink said.

Coastal GasLink added that hydrotesting is either complete or underway in every section, a “critically important phase” of the project that ensures it can safely transition its infrastructure into operations.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is about 85 percent complete and recently completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Worley gets full notice to proceed on first phase of CP2 LNG project

Australian engineering firm Worley has received a full notice to proceed from US LNG exporter Venture Global LNG under its reimbursable EPC contract for the first phase of the CP2 LNG project in Louisiana.

Venture Global’s Plaquemines LNG to commission fourth tank

US LNG exporter Venture Global LNG has received approval from the US FERC to commission the fourth storage tank with LNG at its Plaquemines plant in Louisiana.

MOL’s LNG carrier fleet stands at 104 vessels

MOL's large fleet of liquefied natural gas (LNG) tankers had 104 vessels as of the end of June this year.

More News Like This

Fluor, JGC score FEED job for LNG Canada expansion

A joint venture of US engineer Fluor and Japan's JGC has been awarded the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the Shell-led LNG Canada project.

Shell CEO says LNG Canada ramp-up in line with expectations

LNG Canada's production ramp-up is "very much" in line with what Shell had expected, according to Shell CEO Wael Sawan.

South Korea gets first LNG Canada cargo

The 174,000-cbm GasLog Glasgow, which is carrying the first liquefied natural gas cargo produced at the Shell-led LNG Canada facility in Kitimat, has arrived in Tongyeong, South Korea, according to shipping data.

LNG Canada to send third cargo

Shell-led LNG Canada is expected to soon ship the third cargo of liquefied natural gas from the Kitimat facility, according to shipping data.