LNG Canada pipeline almost 92 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 92 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in a construction update the pipeline has achieved 91.4 percent overall completion and it still expects to complete the project by the end of 2023.

“Our workforce of nearly 4,800 are focused on safely completing remaining critical items across the 670-kilometre project route this summer, while ensuring important environmental management measures are in place,” it said.

“With more than 630 km of pipe installed, crews are busy completing distinct work fronts such as water crossings and steep slopes. To date, more than 92 percent of all classified water crossings are complete, and steep slope areas such as Cable Crane Hill and the Raised Bore, continue to make significant strides forward,” Coastal GasLink said.

Coastal GasLink added that hydrotesting is either complete or underway in every section, a “critically important phase” of the project that ensures it can safely transition its infrastructure into operations.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is about 85 percent complete and recently completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

- Advertisements -

Most Popular

Spark: spot LNG shipping rates ease this week

Spot charter rates for the global liquefied natural gas (LNG) carrier fleet declined this week as vessel availability increased,...

Pilot LNG, Seapath plan to build $150 million US bunkering facility

Houston-based Pilot LNG is joining forces with Libra Group's maritime unit Seapath to build what they say is the...

US weekly LNG exports down to 21 shipments

US liquefied natural gas (LNG) exports declined in the week ending September 27 compared to the week before, according...

More News Like This

Second LNG Canada electric tug delivered

HaiSea Marine’s second of three electric tugboats which will serve the Shell-led LNG Canada project is on its way...

GIP to buy stake in two pipelines from TC Energy 

Canada's TC Energy agreed to sell a 40 percent interest in its Columbia Gas and Columbia Gulf pipelines, which...

LNG Canada wraps up tank test

Shell’s LNG Canada and its contractors have completed LNG tank hydro testing at the project site in Kitimat, British...

Shell’s LNG Canada hits new milestone

A joint venture of JGC and Fluor has completed the module fabrication program for Shell's giant LNG Canada project...