LNG Canada pipeline almost 92 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 92 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in a construction update the pipeline has achieved 91.4 percent overall completion and it still expects to complete the project by the end of 2023.

“Our workforce of nearly 4,800 are focused on safely completing remaining critical items across the 670-kilometre project route this summer, while ensuring important environmental management measures are in place,” it said.

“With more than 630 km of pipe installed, crews are busy completing distinct work fronts such as water crossings and steep slopes. To date, more than 92 percent of all classified water crossings are complete, and steep slope areas such as Cable Crane Hill and the Raised Bore, continue to make significant strides forward,” Coastal GasLink said.

Coastal GasLink added that hydrotesting is either complete or underway in every section, a “critically important phase” of the project that ensures it can safely transition its infrastructure into operations.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is about 85 percent complete and recently completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

- Advertisements -

Most Popular

Golden Pass LNG to ramp up construction activities after Zachry deal

QatarEnergy and ExxonMobil will ramp up construction activities at the Golden Pass LNG export terminal in Texas after a...

Hudong-Zhonghua confirms TotalEnergies order for LNG bunkering vessel

China’s Hudong-Zhonghua said it had secured an order to build one 18,600-cbm LNG bunkering vessel for French energy giant...

India was top destination for US LNG cargoes in May

India was the top destination for US liquefied natural gas cargoes in May, as Asia overtook Europe as the...

More News Like This

Fluor and JGC move one step closer to completion of LNG Canada’s first train

US engineer Fluor announced completion of the final weld on the first production train at the Shell-led LNG Canada...

Malaysia’s Petronas adds new vessels to its fleet as LNG Canada launch nears

Malaysian energy giant Petronas has added three new liquefied natural gas (LNG) carriers to its fleet as it prepares...

Ksi Lisims LNG partners to buy Prince Rupert pipeline project from TC Energy

Houston-based Western LNG and the Nisga’a Nation, the partners in Canada's Ksi Lisims LNG project, have agreed to buy...

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...