LNG Canada pipeline almost 95 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 95 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the pipeline has achieved 94.7 percent overall completion and it still expects to complete the project by the end of 2023.

Also, the project achieved 98 percent pipe installation, while 4,820 workers were working across the project route as of August 26, it said.

As of the end of August, all 800 water crossings across the project have also been executed, including all 10 major trenchless water crossings.

LNG Canada pipeline almost 95 percent complete
Image: Coastal GasLink

While the project is quickly approaching mechanical completion at the end of 2023, there are a number of critical activities that the project team will continue to execute on, Coastal GasLink said.

These activities include clean-up and reclamation and erosion and sediment control (ESC) measures.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

LNG Canada pipeline almost 95 percent complete
Image: LNG Canada

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Woodside issues Louisiana LNG construction update

In October 2024, Woodside acquired all issued and outstanding Tellurian common stock for about $900 million cash, or $1.00 per share....

Trump lifts pause on non-FTA LNG export approvals

Trump issued the executive order, which was widely expected, just hours after officially taking over his second four-year term...

Hoegh Evi, SEFE ink hydrogen pact

Norwegian FSRU player Hoegh Evi, previously known as Hoegh LNG, is joining forces with German gas importer Securing Energy...

More News Like This

Shell’s LNG Canada names new CEO

Cooper, currently LNG Canada’s senior vice president for Phase 1 pipeline and expansion will succeed Jason Klein as president...

LNG Canada pipeline enters commercial service

Canada's TC Energy said on Tuesday CGL had executed a commercial agreement with LNG Canada and CGL customers that...

Woodfibre LNG appoints new CEO

According to a Woodfibre LNG statement, Schauerte brings more than 20 years of experience in the Canadian and global...

Shell’s LNG Canada starts cooldown activities

LNG Canada previously said it would receive a cargo of refrigerants (liquefied petroleum gas) onboard the tanker Gaschem Atlantic. The...