LNG Canada pipeline almost 95 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 95 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the pipeline has achieved 94.7 percent overall completion and it still expects to complete the project by the end of 2023.

Also, the project achieved 98 percent pipe installation, while 4,820 workers were working across the project route as of August 26, it said.

As of the end of August, all 800 water crossings across the project have also been executed, including all 10 major trenchless water crossings.

LNG Canada pipeline almost 95 percent complete
Image: Coastal GasLink

While the project is quickly approaching mechanical completion at the end of 2023, there are a number of critical activities that the project team will continue to execute on, Coastal GasLink said.

These activities include clean-up and reclamation and erosion and sediment control (ESC) measures.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

LNG Canada pipeline almost 95 percent complete
Image: LNG Canada

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Shell adds another LNG carrier to its fleet

A unit of UK-based LNG giant Shell has added another chartered liquefied natural gas carrier to its fleet.

CMA CGM’s LNG-powered giant floated out in China

China’s Hudong-Zhonghua has launched the third in a new series of 24,000-teu LNG dual-fuel containerships for French shipping giant CMA CGM.

Venture Global gets OK to introduce gas to final Plaquemines LNG block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the 18th and final liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Shell’s LNG Canada seeks OK to boost export capacity

Shell-led LNG Canada is seeking approval from the Canadian energy regulator to boost its annual export capacity by 6.4 percent.

Fluor, JGC score FEED job for LNG Canada expansion

A joint venture of US engineer Fluor and Japan's JGC has been awarded the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the Shell-led LNG Canada project.

Shell CEO says LNG Canada ramp-up in line with expectations

LNG Canada's production ramp-up is "very much" in line with what Shell had expected, according to Shell CEO Wael Sawan.

South Korea gets first LNG Canada cargo

The 174,000-cbm GasLog Glasgow, which is carrying the first liquefied natural gas cargo produced at the Shell-led LNG Canada facility in Kitimat, has arrived in Tongyeong, South Korea, according to shipping data.