LNG Canada pipeline almost 95 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 95 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the pipeline has achieved 94.7 percent overall completion and it still expects to complete the project by the end of 2023.

Also, the project achieved 98 percent pipe installation, while 4,820 workers were working across the project route as of August 26, it said.

As of the end of August, all 800 water crossings across the project have also been executed, including all 10 major trenchless water crossings.

LNG Canada pipeline almost 95 percent complete
Image: Coastal GasLink

While the project is quickly approaching mechanical completion at the end of 2023, there are a number of critical activities that the project team will continue to execute on, Coastal GasLink said.

These activities include clean-up and reclamation and erosion and sediment control (ESC) measures.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

LNG Canada pipeline almost 95 percent complete
Image: LNG Canada

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Coastal Bend LNG plans large Texas export plant

Coastal Bend LNG said it had initiated development of a 22.5 million ton per annum (mtpa) natural gas liquefaction and export facility on the Texas Gulf Coast.

HD Hyundai Samho scores contract to build LNG carrier quartet

South Korea’s HD Hyundai Samho has secured an order to build four liquefied natural gas (LNG) carriers for about $1.03 billion.

Golden Pass LNG contractors agree terms for second and third train

Japan's Chiyoda and US-based McDermott have signed a binding term sheet with Golden Pass LNG, a joint venture owned by QatarEnergy and ExxonMobil, to complete the construction of the second and third liquefaction units at the giant LNG export plant in Texas.

More News Like This

Shell’s LNG Canada achieves first LNG

LNG giant Shell has started production at the first liquefaction train at its LNG Canada export terminal in Kitimat, an LNG Canada spokesperson told LNG Prime on Sunday.

Shell’s LNG Canada nears first LNG

LNG giant Shell is nearing the launch of the first liquefaction train at its LNG Canada export terminal in Kitimat.

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.

Chris Cooper takes over as LNG Canada CEO

Chris Cooper has taken over as president and chief executive officer of LNG Canada as the Shell-led JV prepares to ship the first LNG cargoes from the Kitimat facility.