LNG Canada pipeline almost 95 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 95 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the pipeline has achieved 94.7 percent overall completion and it still expects to complete the project by the end of 2023.

Also, the project achieved 98 percent pipe installation, while 4,820 workers were working across the project route as of August 26, it said.

As of the end of August, all 800 water crossings across the project have also been executed, including all 10 major trenchless water crossings.

LNG Canada pipeline almost 95 percent complete
Image: Coastal GasLink

While the project is quickly approaching mechanical completion at the end of 2023, there are a number of critical activities that the project team will continue to execute on, Coastal GasLink said.

These activities include clean-up and reclamation and erosion and sediment control (ESC) measures.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

LNG Canada pipeline almost 95 percent complete
Image: LNG Canada

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

MOL’s large LNG carrier fleet expands

The Jaanpese shipping firm said in its results report it had 100 LNG vessels at the end of September...

US sanctions four LNG carrier owners

The Department of State said in a statement on Wednesday that it continues to designate entities involved in the...

Samsung Heavy scores LNG carrier order

Samsung Heavy said on Thursday that it will build the LNG carrier for an unidentified owner in Asia. The shipbuilder...

More News Like This

Shell’s LNG Canada starts cooldown activities

LNG Canada previously said it would receive a cargo of refrigerants (liquefied petroleum gas) onboard the tanker Gaschem Atlantic. The...

Shell’s LNG Canada terminal more than 95 percent complete

Klein said in the newest project update on Thursday that 35,000-plus individual Canadians have worked on the LNG Canada...

Shell’s LNG Canada to introduce gas to Kitimat terminal

LNG Canada revealed this in a statement on Thursday. "Once natural gas is received from the Coastal GasLink pipeline and...

LNG Canada to get LPG cargo as part of commissioning phase

LNG Canada said in a statement on Wednesday that it continues to conduct commissioning and safe start-up activities for...