LNG Canada pipeline almost 95 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 95 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the pipeline has achieved 94.7 percent overall completion and it still expects to complete the project by the end of 2023.

Also, the project achieved 98 percent pipe installation, while 4,820 workers were working across the project route as of August 26, it said.

As of the end of August, all 800 water crossings across the project have also been executed, including all 10 major trenchless water crossings.

LNG Canada pipeline almost 95 percent complete
Image: Coastal GasLink

While the project is quickly approaching mechanical completion at the end of 2023, there are a number of critical activities that the project team will continue to execute on, Coastal GasLink said.

These activities include clean-up and reclamation and erosion and sediment control (ESC) measures.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

LNG Canada pipeline almost 95 percent complete
Image: LNG Canada

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

- Advertisements -

Most Popular

NYK’s LNG carrier fleet expands to 91 vessels

Japan’s shipping giant NYK said its fleet of operational liquefied natural gas (LNG) carriers rose to 91 vessels by...

Sempra says ECA LNG export project more than 80 percent complete

US LNG exporter Sempra said that construction of the first phase of its Energía Costa Azul LNG export project...

Sempra updates on Port Arthur LNG work

US LNG exporter Sempra and compatriot engineering and construction firm Bechtel are moving forward with construction on the first...

More News Like This

Ksi Lisims LNG partners to buy Prince Rupert pipeline project from TC Energy

Houston-based Western LNG and the Nisga’a Nation, the partners in Canada's Ksi Lisims LNG project, have agreed to buy...

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...

LNG Canada CEO: start-up activities will take more than a year to complete

Shell's LNG Canada project is now preparing to launch start-up activities next year and this program will take more...

HaiSea Marine takes delivery of its first LNG-powered tug

Turkey’s Sanmar has delivered the first of two LNG-powered tugs to Canada's HaiSea Marine, a joint venture majority owned...