LNG Canada pipeline almost 95 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is almost 95 percent complete.

The 670 kilometers long pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

Coastal GasLink said in its latest construction update that the pipeline has achieved 94.7 percent overall completion and it still expects to complete the project by the end of 2023.

Also, the project achieved 98 percent pipe installation, while 4,820 workers were working across the project route as of August 26, it said.

As of the end of August, all 800 water crossings across the project have also been executed, including all 10 major trenchless water crossings.

LNG Canada pipeline almost 95 percent complete
Image: Coastal GasLink

While the project is quickly approaching mechanical completion at the end of 2023, there are a number of critical activities that the project team will continue to execute on, Coastal GasLink said.

These activities include clean-up and reclamation and erosion and sediment control (ESC) measures.

The price tag of the giant pipeline has increased substantially over the years and TC Energy now estimates costs for the first phase of its pipeline to reach C$14.5 billion.

LNG Canada pipeline almost 95 percent complete
Image: LNG Canada

As per the LNG Canada plant, the project built by JGC Fluor was about 85 percent complete in July and during the same month it completed LNG tank hydro testing at the project site in Kitimat, British Columbia.

Besides Shell, other partners in Canada’s first LNG export terminal include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

The first phase of the LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa in Kitimat.

Shell and its partners and are also evaluating the second phase of the project.

Most Popular

Glencore pens Chinese LNG supply deal

Switzerland-based energy trader Glencore has signed a long-term deal to supply liquefied natural gas (LNG) to a unit of China Suntien Green Energy.

Equinor seals long-term LNG SPA with Thailand’s PTT

Norwegian energy firm Equinor has signed a long-term LNG sales and purchase agreement with a unit of Thailand’s PTT.

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

More News Like This

Shell CEO: LNG Canada Phase 2 FID likely by end of this year

Shell CEO Wael Sawan confirmed on Thursday that the company and its LNG Canada partners expect to take a final investment decision on the second phase of the project by the end of this year.

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.

LNG Canada ships 100th cargo

Shell-led LNG Canada has shipped the 100th cargo of liquefied natural gas from its Kitimat facility on the west coast of Canada.

PetroVietnam Gas receives Canadian LNG cargo

PetroVietnam Gas, a unit of state-owned PetroVietnam, has received a cargo of liquefied natural gas from Canada as it increases LNG imports amid disruptions caused by the Middle East conflict.