LNG Canada pipeline more than 62 percent done

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, is moving forward with the construction of the pipeline in British Columbia in order to complete it in 2023.

Coastal GasLink said in an update the overall progress had reached 62.4 percent, compared to about 60 percent last month when it signed a stake sale deal with Indigenous communities.

It has also completed two of eight sections along the the 670 km long route.

Both Section 1, west of Dawson Creek and Section 4, north of Prince George, have achieved 100 percent pipe installation, Coastal GasLink said.

“Completing these sections provides a solid foundation to build on as we focus on safely completing the remaining sections of the 670 kilometer pipeline as projected in 2023,” the firm said.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat.

LNG Canada said in May it was reaching the 60 percent completion mark after it received a large module from China.

Also, the developer of the 14 mtpa LNG export plant in Kitimat recently appointed Jason Klein as its new chief executive and said it remains on track to deliver its first cargo by the middle of this decade.

Besides operator Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Shell adds another LNG carrier to its fleet

A unit of UK-based LNG giant Shell has added another chartered liquefied natural gas carrier to its fleet.

Chevron, China’s ENN seal second LNG SPA

US energy giant Chevron has signed a second LNG sales and purchase agreement with Chinese independent gas distributor ENN.

Venture Global gets OK to introduce gas to final Plaquemines LNG block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the 18th and final liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Shell’s LNG Canada seeks OK to boost export capacity

Shell-led LNG Canada is seeking approval from the Canadian energy regulator to boost its annual export capacity by 6.4 percent.

Fluor, JGC score FEED job for LNG Canada expansion

A joint venture of US engineer Fluor and Japan's JGC has been awarded the contract to update the front-end engineering and design (FEED) for a proposed Phase 2 expansion of the Shell-led LNG Canada project.

Shell CEO says LNG Canada ramp-up in line with expectations

LNG Canada's production ramp-up is "very much" in line with what Shell had expected, according to Shell CEO Wael Sawan.

South Korea gets first LNG Canada cargo

The 174,000-cbm GasLog Glasgow, which is carrying the first liquefied natural gas cargo produced at the Shell-led LNG Canada facility in Kitimat, has arrived in Tongyeong, South Korea, according to shipping data.