LNG Canada pipeline more than 62 percent done

TC Energy’s Coastal GasLink project, which will supply natural gas to the Shell-led LNG Canada export terminal, is moving forward with the construction of the pipeline in British Columbia in order to complete it in 2023.

Coastal GasLink said in an update the overall progress had reached 62.4 percent, compared to about 60 percent last month when it signed a stake sale deal with Indigenous communities.

It has also completed two of eight sections along the the 670 km long route.

Both Section 1, west of Dawson Creek and Section 4, north of Prince George, have achieved 100 percent pipe installation, Coastal GasLink said.

“Completing these sections provides a solid foundation to build on as we focus on safely completing the remaining sections of the 670 kilometer pipeline as projected in 2023,” the firm said.

Coastal GasLink will move at least 2.1 billion cubic feet per day of natural gas with the potential for delivery of up to 5 bcf/d from the Dawson Creek area to the LNG Canada facility in Kitimat.

LNG Canada said in May it was reaching the 60 percent completion mark after it received a large module from China.

Also, the developer of the 14 mtpa LNG export plant in Kitimat recently appointed Jason Klein as its new chief executive and said it remains on track to deliver its first cargo by the middle of this decade.

Besides operator Shell, LNG Canada partners include Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

- Advertisements -

Most Popular

Golden Pass LNG to ramp up construction activities after Zachry deal

QatarEnergy and ExxonMobil will ramp up construction activities at the Golden Pass LNG export terminal in Texas after a...

Tellurian updates on Driftwood LNG work

US LNG terminal developer Tellurian, which is being acquired by Australia's Woodside, released the latest construction update for the...

Hudong-Zhonghua confirms TotalEnergies order for LNG bunkering vessel

China’s Hudong-Zhonghua said it had secured an order to build one 18,600-cbm LNG bunkering vessel for French energy giant...

More News Like This

Fluor and JGC move one step closer to completion of LNG Canada’s first train

US engineer Fluor announced completion of the final weld on the first production train at the Shell-led LNG Canada...

Malaysia’s Petronas adds new vessels to its fleet as LNG Canada launch nears

Malaysian energy giant Petronas has added three new liquefied natural gas (LNG) carriers to its fleet as it prepares...

Ksi Lisims LNG partners to buy Prince Rupert pipeline project from TC Energy

Houston-based Western LNG and the Nisga’a Nation, the partners in Canada's Ksi Lisims LNG project, have agreed to buy...

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...