LNG Canada pipeline more than 81 percent complete

TC Energy’s Coastal GasLink is moving forward with works on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal, as it enters the final year of construction.

Coastal GasLink said in a construction update last week that the overall progress on the project had reached 81.2 percent completion as of the end of November.

Some of the most notable achievements this year include the 100 percent pipe install in sections 1 and 4, the completion of the Wilde Lake compressor station, and the start of pipe install at Cable Crane Hill, which has reached 45 percent pipe install ahead of schedule, it said.

To date, Coastal GasLink has installed more than 490 km of pipe across the 670-km route, according to the firm.

“Overall, our team has spent more than 38 million hours working on this project, with more than 6,000 women and men employed at our peak,” the firm said.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Another FSRU arrives in Egypt

The 160,000-cbm FSRU Energos Eskimo has arrived in Egypt from Jordan, according to shipping data. The unit is one of four FSRUs that will serve a charter deal with Egypt's EGAS as the country seeks to meet its growing demand for natural gas.

Venture Global’s Plaquemines LNG to commission third jetty

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce hazardous fluids to the third jetty at its Plaquemines LNG export plant in Louisiana.

MOL’s LNG carrier to feature SOFC tech

Japan's MOL and South Korea's Samsung Heavy Industries have received approval from classification society LR for the design of a 174,000-cbm LNG carrier integrating solid oxide fuel fell (SOFC) technology.

More News Like This

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.

Chris Cooper takes over as LNG Canada CEO

Chris Cooper has taken over as president and chief executive officer of LNG Canada as the Shell-led JV prepares to ship the first LNG cargoes from the Kitimat facility.

Update: Shell’s LNG Canada receives LNG cargo

Shell’s LNG Canada has received a cargo of liquefied natural gas as part of the commissioning and start-up phase.

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.