LNG Canada pipeline more than 81 percent complete

TC Energy’s Coastal GasLink is moving forward with works on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal, as it enters the final year of construction.

Coastal GasLink said in a construction update last week that the overall progress on the project had reached 81.2 percent completion as of the end of November.

Some of the most notable achievements this year include the 100 percent pipe install in sections 1 and 4, the completion of the Wilde Lake compressor station, and the start of pipe install at Cable Crane Hill, which has reached 45 percent pipe install ahead of schedule, it said.

To date, Coastal GasLink has installed more than 490 km of pipe across the 670-km route, according to the firm.

“Overall, our team has spent more than 38 million hours working on this project, with more than 6,000 women and men employed at our peak,” the firm said.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Australia’s Santos strengthens LNG portfolio with new deals

Australian LNG player Santos has signed two separate, non-binding LNG agreements that underscore the company’s growing global LNG portfolio position. Santos entered into a non-binding heads of agreement to buy LNG from the Ksi Lisims LNG project in Canada and the company agreed key commercial terms with South Korea's Posco Steel to supply the latter with LNG.

Fluxys: Dunkirk LNG sendout reduced due to strike

France’s Dunkirk LNG import terminal has reduced sendout to the grid on Tuesday due to a strike, according to Belgian LNG terminal operator Fluxys.

Sempra Infrastructure, Petrobras ink 20-year Port Arthur LNG SPA

Brazil’s state-owned energy firm Petrobras has signed a long-term deal with US LNG exporter Sempra Infrastructure, a unit of Sempra, to buy LNG from the second phase of the Port Arthur LNG project in Texas.

More News Like This

Shell CEO: LNG Canada Phase 2 FID likely by end of this year

Shell CEO Wael Sawan confirmed on Thursday that the company and its LNG Canada partners expect to take a final investment decision on the second phase of the project by the end of this year.

LNG Canada offers option to First Nations to invest in Phase 2 storage tank

Shell-led LNG Canada has signed an agreement with five northwestern B.C. First Nations, giving them the option to invest up to C$1 billion ($711 million) to acquire an LNG storage tank slated for construction as part of the expansion of its Kitimat LNG export facility on the west coast of Canada.

LNG Canada ships 100th cargo

Shell-led LNG Canada has shipped the 100th cargo of liquefied natural gas from its Kitimat facility on the west coast of Canada.

PetroVietnam Gas receives Canadian LNG cargo

PetroVietnam Gas, a unit of state-owned PetroVietnam, has received a cargo of liquefied natural gas from Canada as it increases LNG imports amid disruptions caused by the Middle East conflict.