LNG Canada pipeline more than 81 percent complete

TC Energy’s Coastal GasLink is moving forward with works on the giant pipeline that will supply natural gas to the Shell-led LNG Canada export terminal, as it enters the final year of construction.

Coastal GasLink said in a construction update last week that the overall progress on the project had reached 81.2 percent completion as of the end of November.

Some of the most notable achievements this year include the 100 percent pipe install in sections 1 and 4, the completion of the Wilde Lake compressor station, and the start of pipe install at Cable Crane Hill, which has reached 45 percent pipe install ahead of schedule, it said.

To date, Coastal GasLink has installed more than 490 km of pipe across the 670-km route, according to the firm.

“Overall, our team has spent more than 38 million hours working on this project, with more than 6,000 women and men employed at our peak,” the firm said.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, with the potential to boost it further.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023 but the costs will significantly rise.

In July, LNG Canada and TC Energy reached a revised deal for the pipeline. The project now has a price tag of C$11.2 billion.

However, the project costs continue to rise and TC Energy said in November that the firm expects a “material increase in project costs” and TC Energy’s corresponding funding requirements.

As per the LNG Canada plant in Kitimat, the project is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

- Advertisements -

Most Popular

South Korean yards built 500 LNG carriers for export in 30 years

South Korean yards have completed 500 liquefied natural gas (LNG) tankers for export since 1994, according to the Ministry...

MARAD: Delfin needs to submit amended application for FLNG project

The US Maritime Administration (MARAD) said that Delfin LNG needs to file an amended application for its floating LNG...

Report: Egypt’s EGAS charters Hoegh LNG’s FSRU

The Egyptian Natural Gas Holding Company (EGAS) has chartered Hoegh LNG's floating storage regasification and storage unit, Hoegh Galleon,...

More News Like This

Ksi Lisims LNG partners to buy Prince Rupert pipeline project from TC Energy

Houston-based Western LNG and the Nisga’a Nation, the partners in Canada's Ksi Lisims LNG project, have agreed to buy...

Shell CEO: LNG Canada to start commissioning later this year

Shell’s LNG Canada terminal is more than 90 percent complete and the project is preparing to launch commissioning activities...

LNG Canada CEO: start-up activities will take more than a year to complete

Shell's LNG Canada project is now preparing to launch start-up activities next year and this program will take more...

HaiSea Marine takes delivery of its first LNG-powered tug

Turkey’s Sanmar has delivered the first of two LNG-powered tugs to Canada's HaiSea Marine, a joint venture majority owned...