LNG Canada pipeline more than 85 percent complete

TC Energy’s Coastal GasLink pipeline, which will supply natural gas to the Shell-led LNG Canada terminal, is more than 85 percent complete and recently reached a new milestone.

Coastal GasLink said in a construction update that the overall progress on the project reached 85.5 percent completion as of the end of February.

There were 5,489 workers employed across the project route as of February 28.

Last month, TC Energy said that the pipeline was 84 percent complete, while the firm is also evaluating the second phase of the project.

The Canadian firm now estimates costs for the first phase of its giant 670 kilometers long pipeline to reach C$14.5 billion ($10.7 billion).

First gas

According to Coastal GasLink, the Wilde Lake Compressor station, which serves as the starting point for the natural gas pipeline, is now introducing natural gas into the system as part of the transition to operations.

“As the project surpasses 85 percent completion, this is a significant milestone that brings Coastal GasLink one step closer to delivering critical Canadian LNG to world markets,” it said.

The Wilde Lake facility consists of three compressor units and four meter stations.

Moreover, the meter stations receive and measure the incoming gas from Coastal GasLink’s customers, and the compressor units then compresses the gas to provide the pressure required to deliver the gas 670 kilometers to LNG Canada’s site in Kitimat.

The pipeline will have the capacity to transport 2.1 billion cubic feet of natural gas per day (bcf/d) from Groundbirch, BC to Kitimat, in the first phase.

TC Energy expects to reach mechanical in-service of the pipeline by the end of 2023.

LNG Canada pipeline more than 85 percent complete
Wilde Lake compressor station (Image: Coastal GasLink)

As per the LNG Canada plant in Kitimat, the project built by JGC Fluor is more than 70 percent complete.

The first phase of the giant LNG Canada project includes building two liquefaction trains with a capacity of 14 mtpa.

LNG Canada expects to deliver its first cargo by the middle of this decade.

Besides operator Shell, other partners in LNG Canada are Malaysia’s Petronas, PetroChina, Japan’s Mitsubishi Corporation, and South Korea’s Kogas.

Most Popular

Taiwan’s CPC inks initial Alaska LNG deal

Taiwan’s CPC Corp has signed a letter of intent with Alaska Gasline Development Corporation (AGDC) to buy LNG and invest in the latter's planned Alaska LNG project.

DET terminates Stade FSRU contract with HEH

State-owned German LNG terminal operator DET has terminated the contract related to the Stade FSRU-based facility with compatriot Hanseatic Energy Hub, the developer of the onshore LNG terminal in Stade.

Venture Global’s CP2 LNG project gets non-FTA approval from DOE

US LNG exporter Venture Global LNG has received conditional non-FTA approval from the US Department of Energy for its proposed CP2 LNG project in Louisiana.

More News Like This

Shell’s LNG Canada set to receive LNG cargo as part of commissioning activities

Shell’s LNG Canada is set to receive a cargo of liquefied natural gas onboard the 173,400-cbm LNG carrier, Maran Gas Roxana, as part of the commissioning and start-up phase, a spokesman for LNG Canada told LNG Prime.

Shell’s LNG Canada moving forward with commissioning activities

Shell’s LNG Canada is moving forward with its commissioning and start-up phase and expects to receive a liquefied natural gas (LNG) cargo soon.

Shell still expects mid-year launch for LNG Canada

Shell's finance chief, Sinead Gorman, told analysts during Shell's fourth-quarter earnings call on Thursday that LNG Canada is making...

Shell’s LNG Canada names new CEO

Cooper, currently LNG Canada’s senior vice president for Phase 1 pipeline and expansion will succeed Jason Klein as president...