Marathon’s unit seeks more time for Kenai LNG import project

Marathon’s unit Trans-Foreland Pipeline asked US energy regulators for more time to bring the closed Kenai LNG export plant in Alaska back online as an import facility.

The US Federal Energy Regulatory Commission (FERC) authorized Trans-Foreland on December 17, 2020 to launch the LNG import facility in two years.

Trans-Foreland plans to construct, modify, and operate new facilities for the import of LNG at its existing Kenai LNG export terminal in Nikiski, Kenai Peninsula Borough, and deliver the fuel to its Kenai refinery adjacent to the plant.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

However, Trans-Foreland “does not anticipate being able to place the project into service by December 17, 2022, despite good faith efforts to do so,” according to a filling with FERC dated July 7.

The firm is seeking a three-year extension of time to place the project into service by December 17, 2025.

“Uncertainty and volatility” in global LNG market

According to the filling, “the onset and duration of the Covid-19 pandemic and the war in Ukraine have generated adverse economic and logistical conditions that slowed commercial progress and precluded Trans-Foreland from making its final investment decision (FID) for the project.”

In particular, “uncertainty and volatility in the global LNG market have made it difficult” for Trans-Foreland to secure a suitable supply arrangement that would provide the financial certainty necessary for the project, it said.

Trans-Foreland said it still needs this financial certainty in order to make its FID and move forward with physical modifications to the Kenai LNG terminal.

TransForeland also said it had been actively seeking suitable suppliers and is monitoring markets for LNG.

Despite this delay, Trans-Foreland “is confident that the project continues to be commercially viable,” it said.

Most Popular

Venture Global to start CP2 LNG construction after FERC approval

US LNG exporter Venture Global LNG plans to start construction of its CP2 LNG project in Louisiana "immediately" following approval from the US FERC.

LNG carrier anchors offshore Germany’s Mukran after grounding

The 138,000-cbm LNG carrier Iberica Knutsen was on Friday anchored offshore Mukran, the home of the Deutsche ReGas-operated FSRU-based LNG import facility, following a grounding incident. Deutsche ReGas told LNG Prime that unloading of the vessel's LNG cargo is "part of ongoing operational planning."

HD Hyundai Mipo clinches order for LNG bunkering duo

South Korea’s HD Hyundai Mipo has won a new order to build two liquefied natural gas (LNG) bunkering vessels.

More News Like This

Venture Global to start CP2 LNG construction after FERC approval

US LNG exporter Venture Global LNG plans to start construction of its CP2 LNG project in Louisiana "immediately" following approval from the US FERC.

Freeport LNG production hits record in April

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, said it had achieved record LNG production in April due to the completion of a debottlenecking project. The LNG terminal operator also placed its third LNG tank back into commercial operations following the facility's June 2022 overpressure incident.

Freeport LNG seeks OK to return third tank to commercial service

Freeport LNG, the operator of the three-train 15 mtpa liquefaction plant in Texas, is seeking regulatory approval to place its third LNG tank back into commercial operations following the facility's June 2022 overpressure incident.

US FERC issues final SEIS for Commonwealth LNG’s project

The US Federal Energy Regulatory Commission (FERC) has released a final supplemental environmental impact statement for Commonwealth LNG's proposed LNG export plant in Louisiana. The regulator concluded that National Ambient Air Quality Standards (NAAQS) exceedances for 1-hour NO2 may be significant.