Marathon’s unit seeks more time for Kenai LNG import project

Marathon’s unit Trans-Foreland Pipeline asked US energy regulators for more time to bring the closed Kenai LNG export plant in Alaska back online as an import facility.

The US Federal Energy Regulatory Commission (FERC) authorized Trans-Foreland on December 17, 2020 to launch the LNG import facility in two years.

Trans-Foreland plans to construct, modify, and operate new facilities for the import of LNG at its existing Kenai LNG export terminal in Nikiski, Kenai Peninsula Borough, and deliver the fuel to its Kenai refinery adjacent to the plant.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

However, Trans-Foreland “does not anticipate being able to place the project into service by December 17, 2022, despite good faith efforts to do so,” according to a filling with FERC dated July 7.

The firm is seeking a three-year extension of time to place the project into service by December 17, 2025.

“Uncertainty and volatility” in global LNG market

According to the filling, “the onset and duration of the Covid-19 pandemic and the war in Ukraine have generated adverse economic and logistical conditions that slowed commercial progress and precluded Trans-Foreland from making its final investment decision (FID) for the project.”

In particular, “uncertainty and volatility in the global LNG market have made it difficult” for Trans-Foreland to secure a suitable supply arrangement that would provide the financial certainty necessary for the project, it said.

Trans-Foreland said it still needs this financial certainty in order to make its FID and move forward with physical modifications to the Kenai LNG terminal.

TransForeland also said it had been actively seeking suitable suppliers and is monitoring markets for LNG.

Despite this delay, Trans-Foreland “is confident that the project continues to be commercially viable,” it said.

Most Popular

BP, Venture Global to supply LNG to Bulgargaz in January and February

Bulgargaz previously sought two LNG cargoes for delivery during January and February 2025. The company recently announced that 19 international...

Geocean kicks off work on Congo FLNG mooring project

French marine and offshore contractor, Geocean, a VINCI Construction Grands Projets unit, has started working on a new contract...

Petronas, CNPC strengthen LNG ties

Malaysia's Petronas and China National Petroleum Corporation (CNPC) signed a memorandum of understanding (MoU) to strengthen collaboration in various...

More News Like This

Venture Global moving forward with Plaquemines LNG commissioning

The regulator said in a filing dated November 6 that it grated Venture Global Plaquemines LNG's request to commission...

Golden Pass secures three-year extension to complete Texas LNG terminal

Under the original FERC order from 2016, Golden Pass LNG was required to complete and place into service the...

Cheniere’s Corpus Christi expansion project nears launch of LNG production

"Together with Bechtel, we continue to advance our Corpus Christi Stage 3 project ahead of schedule and anticipate achieving...

Venture Global’s Plaquemines LNG to commission fourth liquefaction block with nitrogen

According to a filing, the regulator approved the commissioning of the block on October 16. The FERC granted the commissioning...