Marathon’s unit seeks more time for Kenai LNG import project

Marathon’s unit Trans-Foreland Pipeline asked US energy regulators for more time to bring the closed Kenai LNG export plant in Alaska back online as an import facility.

The US Federal Energy Regulatory Commission (FERC) authorized Trans-Foreland on December 17, 2020 to launch the LNG import facility in two years.

Trans-Foreland plans to construct, modify, and operate new facilities for the import of LNG at its existing Kenai LNG export terminal in Nikiski, Kenai Peninsula Borough, and deliver the fuel to its Kenai refinery adjacent to the plant.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

However, Trans-Foreland “does not anticipate being able to place the project into service by December 17, 2022, despite good faith efforts to do so,” according to a filling with FERC dated July 7.

The firm is seeking a three-year extension of time to place the project into service by December 17, 2025.

“Uncertainty and volatility” in global LNG market

According to the filling, “the onset and duration of the Covid-19 pandemic and the war in Ukraine have generated adverse economic and logistical conditions that slowed commercial progress and precluded Trans-Foreland from making its final investment decision (FID) for the project.”

In particular, “uncertainty and volatility in the global LNG market have made it difficult” for Trans-Foreland to secure a suitable supply arrangement that would provide the financial certainty necessary for the project, it said.

Trans-Foreland said it still needs this financial certainty in order to make its FID and move forward with physical modifications to the Kenai LNG terminal.

TransForeland also said it had been actively seeking suitable suppliers and is monitoring markets for LNG.

Despite this delay, Trans-Foreland “is confident that the project continues to be commercially viable,” it said.

Most Popular

Another steam LNG carrier sold for demolition

An NYK-managed steam liquefied natural gas (LNG) carrier has been sold for demolition, according to brokers.

Canada approves Ksi Lisims LNG project

According to a statement on Monday, Julie Dabrusin, Minister of Environment and Climate Change, issued her decision under the...

Abaxx sees significant volume growth in its LNG futures

Abaxx Commodity Futures Exchange, a wholly owned subsidiary of Abaxx Technologies (CBOE:ABXX) has seen significant volume growth in its physically deliverable LNG futures during the past summer months, according to Abaxx Exchange Chief Commercial Officer Joe Raia.

More News Like This

Golden Pass gets OK to place MP 33 compressor station in service

Golden Pass LNG, a joint venture owned by energy giants QatarEnergy and ExxonMobil, has secured approval from the US FERC to place into service its MP 33 compressor station, as it continues to move forward with commissioning activities at its three-train LNG plant in Texas.

Cheniere’s Corpus Christi expansion project almost 88 percent complete

The Stage 3 expansion project at Cheniere’s Corpus Christi LNG export plant in Texas is almost 88 percent complete, while Cheniere has also started site preparation activities for two more midscale trains.

NextDecade’s Rio Grande LNG secures final FERC approval

The US Federal Energy Regulatory Commission (FERC) has issued its final order for NextDecade's Rio Grande LNG facility and the accompanying pipeline in Texas.

Sempra seeks OK to start construction activities for Port Arthur LNG expansion

US LNG exporter Sempra is seeking approval from the Federal Energy Regulatory Commission to start some construction activities for the second phase of the Port Arthur LNG project in Texas, as it continues to work on a final investment decision on the project.