Marathon’s unit seeks more time for Kenai LNG import project

Marathon’s unit Trans-Foreland Pipeline asked US energy regulators for more time to bring the closed Kenai LNG export plant in Alaska back online as an import facility.

The US Federal Energy Regulatory Commission (FERC) authorized Trans-Foreland on December 17, 2020 to launch the LNG import facility in two years.

Trans-Foreland plans to construct, modify, and operate new facilities for the import of LNG at its existing Kenai LNG export terminal in Nikiski, Kenai Peninsula Borough, and deliver the fuel to its Kenai refinery adjacent to the plant.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

However, Trans-Foreland “does not anticipate being able to place the project into service by December 17, 2022, despite good faith efforts to do so,” according to a filling with FERC dated July 7.

The firm is seeking a three-year extension of time to place the project into service by December 17, 2025.

“Uncertainty and volatility” in global LNG market

According to the filling, “the onset and duration of the Covid-19 pandemic and the war in Ukraine have generated adverse economic and logistical conditions that slowed commercial progress and precluded Trans-Foreland from making its final investment decision (FID) for the project.”

In particular, “uncertainty and volatility in the global LNG market have made it difficult” for Trans-Foreland to secure a suitable supply arrangement that would provide the financial certainty necessary for the project, it said.

Trans-Foreland said it still needs this financial certainty in order to make its FID and move forward with physical modifications to the Kenai LNG terminal.

TransForeland also said it had been actively seeking suitable suppliers and is monitoring markets for LNG.

Despite this delay, Trans-Foreland “is confident that the project continues to be commercially viable,” it said.

Most Popular

TotalEnergies CEO expects US financing for Mozambique LNG to be approved in weeks

In May 2020, EXIM voted to amend the agency's previously approved September 2019 direct loan supporting US exports for...

Greek and German firms place orders for LNG-powered vessels in China and Korea

Reports by Intermodal and other brokers suggest that Greece's Sun Enterprises and TMS Group and Germany's Peter Dohle ordered...

Gastrade: Alexandroupolis FSRU remains offline due to technical issue

"For the moment, regasification services have been suspended due to a technical issue, for which we will provide further...

More News Like This

Harvest, Marathon Petroleum revive Kenai LNG import plans

Harvest Alaska said on Thursday it has signed a deal with Marathon Petroleum (MPC) and Chugach Electric Association to...

FERC: Venture Global nears completion of Calcasieu Pass LNG repairs

Calcasieu Pass produced its first LNG on January 19, 2022, moving from FID to LNG production in 29 months, and the first...

Plaquemines LNG to commission two more liquefaction blocks with nitrogen

According to a filing dated January 13, the regulator approved the commissioning of the liquefaction train system blocks 7...

Cheniere’s Corpus Christi expansion project nears first LNG

According to a filing with the US FERC dated December 20, Corpus Christi Liquefaction requests to introduce FEED gas...