Marathon’s unit seeks more time for Kenai LNG import project

Marathon’s unit Trans-Foreland Pipeline asked US energy regulators for more time to bring the closed Kenai LNG export plant in Alaska back online as an import facility.

The US Federal Energy Regulatory Commission (FERC) authorized Trans-Foreland on December 17, 2020 to launch the LNG import facility in two years.

Trans-Foreland plans to construct, modify, and operate new facilities for the import of LNG at its existing Kenai LNG export terminal in Nikiski, Kenai Peninsula Borough, and deliver the fuel to its Kenai refinery adjacent to the plant.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

However, Trans-Foreland “does not anticipate being able to place the project into service by December 17, 2022, despite good faith efforts to do so,” according to a filling with FERC dated July 7.

The firm is seeking a three-year extension of time to place the project into service by December 17, 2025.

“Uncertainty and volatility” in global LNG market

According to the filling, “the onset and duration of the Covid-19 pandemic and the war in Ukraine have generated adverse economic and logistical conditions that slowed commercial progress and precluded Trans-Foreland from making its final investment decision (FID) for the project.”

In particular, “uncertainty and volatility in the global LNG market have made it difficult” for Trans-Foreland to secure a suitable supply arrangement that would provide the financial certainty necessary for the project, it said.

Trans-Foreland said it still needs this financial certainty in order to make its FID and move forward with physical modifications to the Kenai LNG terminal.

TransForeland also said it had been actively seeking suitable suppliers and is monitoring markets for LNG.

Despite this delay, Trans-Foreland “is confident that the project continues to be commercially viable,” it said.

Most Popular

Oman LNG inks SPA with Thailand’s PTT

PTT revealed the signing of the deal in a statement issued on Thursday. PTT International Trading (PTTT), a unit of...

Crown LNG expects FID on Scottish FSRU terminal in Q2 2025

Crown LNG revealed this in a corporate update released on Wednesday. The company delayed the decision on the Grangemouth FSRU...

Nordsol: Dutch bio-LNG plant launched

Dutch firms Nordsol and Attero launched the bio-LNG plant in Wilp. The facility will produce bio-LNG for the maritime...

More News Like This

Eagle LNG gets more time to build Jacksonville terminal

Back in September 2019, the FERC granted a five-year authorization to Eagle LNG Partners Jacksonville to site, construct, and...

Venture Global’s Plaquemines LNG gets OK to start cooldown activities

According to a FERC filling dated September 6, the regulator grated Venture Global Plaquemines LNG's request to "introduce hazardous...

Golden Pass seeks FERC extension to complete Texas LNG terminal

State-owned QatarEnergy owns a 70 percent stake in the Golden Pass project with a capacity of more than 18...

Venture Global’s Plaquemines LNG terminal gets cool-down cargo

Venture Global posted an image via its social media on Friday of the 2020-built 174,000-cbm, Qogir, at the Plaquemines...