Marathon’s unit seeks more time for Kenai LNG import project

Marathon’s unit Trans-Foreland Pipeline asked US energy regulators for more time to bring the closed Kenai LNG export plant in Alaska back online as an import facility.

The US Federal Energy Regulatory Commission (FERC) authorized Trans-Foreland on December 17, 2020 to launch the LNG import facility in two years.

Trans-Foreland plans to construct, modify, and operate new facilities for the import of LNG at its existing Kenai LNG export terminal in Nikiski, Kenai Peninsula Borough, and deliver the fuel to its Kenai refinery adjacent to the plant.

The Kenai LNG cool down project would allow the plant to provide up to 7 million standard cubic feet per day of gas.

However, Trans-Foreland “does not anticipate being able to place the project into service by December 17, 2022, despite good faith efforts to do so,” according to a filling with FERC dated July 7.

The firm is seeking a three-year extension of time to place the project into service by December 17, 2025.

“Uncertainty and volatility” in global LNG market

According to the filling, “the onset and duration of the Covid-19 pandemic and the war in Ukraine have generated adverse economic and logistical conditions that slowed commercial progress and precluded Trans-Foreland from making its final investment decision (FID) for the project.”

In particular, “uncertainty and volatility in the global LNG market have made it difficult” for Trans-Foreland to secure a suitable supply arrangement that would provide the financial certainty necessary for the project, it said.

Trans-Foreland said it still needs this financial certainty in order to make its FID and move forward with physical modifications to the Kenai LNG terminal.

TransForeland also said it had been actively seeking suitable suppliers and is monitoring markets for LNG.

Despite this delay, Trans-Foreland “is confident that the project continues to be commercially viable,” it said.

Most Popular

Hudong-Zhonghua kicks off construction on first QC-Max LNG carrier

Chinese shipbuilder Hudong-Zhonghua has officially started building the first ultra-large QC-Max LNG carrier as part of the massive QatarEnergy shipbuilding program. The shipbuilder says this is the world's largest LNG carrier.

Asyad Shipping and MOL sell steam LNG carrier

Oman's Asyad Shipping and Japan's MOL have sold their jointly-owned 2001-built steam liquefied natural gas carrier, Sohar LNG.

Duo competing to win New Zealand LNG terminal deal

New Zealand has shortlisted two providers to deliver its first liquefied natural gas (LNG) import terminal.

More News Like This

Cook Inlet LNG seeks OK to start pre-filing process for Alaska FSRU project

Cook Inlet LNG, a unit of Louisiana-based Gardes Holdings, is seeking approval from the US FERC to initiate the pre-filing process for its planned FSRU-based LNG import project in Alaska's Cook Inlet.

NextDecade seeks FERC OK for sixth Rio Grande LNG train

US LNG developer NextDecade is seeking approval from the Federal Energy Regulatory Commission to build and operate the sixth liquefaction train and an additional marine berth at its Rio Grande LNG terminal in the Port of Brownsville, Texas.

NextDecade’s Rio Grande LNG secures FERC extension

NextDecade's Rio Grande LNG has secured a three-year extension from the US FERC to complete construction and place into service five trains at its LNG export plant in Texas.

Jera seeks OK to start pre-filing process for Hawaii LNG project

Japan's power firm and LNG trader Jera is seeking approval from the US FERC to initiate the pre-filing process for its planned FSRU-based LNG import facility in Hawaii.