NextDecade expects Rio Grande LNG FID in second half of 2022

US liquefaction plant developer NextDecade now expects to take a final investment decision to build its proposed Rio Grande LNG export plant in Texas in the second half of 2022.

This means that NextDecade delayed the FID for more than six months as it previously said it had expected to take the decision by the end of 2021.

NextDecade first plans to build two liquefaction trains with a capacity of 11 million tonnes per year. The full project would include five trains with a capacity of 27 mtpa.

However, the firm currently has only a 20-year deal with Shell for 2 mtpa of supplies from the proposed Rio Grande plant.

The company is working to sign new deals with a duration of 10-20 years after it plans to work on the project’s financing, according to NextDecade’s newest investor presentation released on Monday.

NextDecade said SPA negotiations were “advancing with multiple counterparties in Europe and Asia” but it did not provide any additional information.

Bechtel contract

The LNG developer has lump-sum turnkey EPC contracts with engineering giant Bechtel.

Also, the duo completed a pricing refresh in March last year and they expect EPC costs for the first two trains, along with two 180,000-cbm tanks and a jetty, to reach about $7.5 billion. The other three trains and associated infrastructure would cost about $10 billion.

All five trains would use Air Products’ C3MR technology and Baker Hughes’ rotating equipment.

Prior to FID, the partners would need to work on the final EPC contract pricing as the current pricing had expired on December 31, 2021, NextDecade said.

Carbon capture

Last year, NextDecade also revealed plans for carbon capture from the LNG export plant.

The firm expects to capture and store more than five million metric tonnes of CO2 per year.

In November, NextDecade filed a limited amendment to its federal authorization with FERC for the LNG terminal that would allow it to voluntarily capture and store CO2 produced at the facility.

The firm said in the presentation it expects to receive approval from FERC for the CCS project in 2022.

Most Popular

Samsung Heavy bags orders for six LNG carriers

South Korean shipbuilding giant Samsung Heavy Industries has secured contracts worth $1.54 billion to build six liquefied natural gas (LNG) carriers.

Flex eyes LNG carrier order

Norwegian owner Flex LNG is exploring with new and existing partners to join the company in ordering new liquefied natural gas (LNG) carriers, according to interim CEO Marius Foss.

Woodside working to charter vessels to ship Louisiana LNG cargoes, CEO says

Australian LNG player Woodside is currently working through how many chartered liquefied natural gas carriers the company will need to ship cargoes from its Louisiana LNG export terminal in the US, according to CEO Meg O’Neill.

More News Like This

Hanwha’s units, Kospo to jointly buy US LNG

South Korea's Hanwha Aerospace and Hanwha Energy, units of Hanwha, are teaming up with compatriot Korea Southern Power (Kospo) to jointly buy US liquefied natural gas (LNG) supplies.

NextDecade secures equity commitments for fourth Rio Grande LNG train

US LNG firm NextDecade has secured up to $1.8 billion in equity commitments from TotalEnergies and Global Infrastructure Partners to finance the construction of the fourth train at its Rio Grande LNG facility in Texas.

NextDecade plans to decide on two Rio Grande LNG trains in September

US LNG firm NextDecade plans to take final investment decisions to build the fourth and fifth trains at the Rio Grande LNG facility in Texas in September.

US FERC issues final SEIS for NextDecade’s Rio Grande LNG project

The US Federal Energy Regulatory Commission (FERC) has released a final supplemental environmental impact statement for NextDecade's Rio Grande LNG facility and the accompanying pipeline in Texas. FERC continues to conclude that approval of the projects would result in "less than significant impacts."