NextDecade expects Rio Grande LNG FID in second half of 2022

US liquefaction plant developer NextDecade now expects to take a final investment decision to build its proposed Rio Grande LNG export plant in Texas in the second half of 2022.

This means that NextDecade delayed the FID for more than six months as it previously said it had expected to take the decision by the end of 2021.

NextDecade first plans to build two liquefaction trains with a capacity of 11 million tonnes per year. The full project would include five trains with a capacity of 27 mtpa.

However, the firm currently has only a 20-year deal with Shell for 2 mtpa of supplies from the proposed Rio Grande plant.

The company is working to sign new deals with a duration of 10-20 years after it plans to work on the project’s financing, according to NextDecade’s newest investor presentation released on Monday.

NextDecade said SPA negotiations were “advancing with multiple counterparties in Europe and Asia” but it did not provide any additional information.

Bechtel contract

The LNG developer has lump-sum turnkey EPC contracts with engineering giant Bechtel.

Also, the duo completed a pricing refresh in March last year and they expect EPC costs for the first two trains, along with two 180,000-cbm tanks and a jetty, to reach about $7.5 billion. The other three trains and associated infrastructure would cost about $10 billion.

All five trains would use Air Products’ C3MR technology and Baker Hughes’ rotating equipment.

Prior to FID, the partners would need to work on the final EPC contract pricing as the current pricing had expired on December 31, 2021, NextDecade said.

Carbon capture

Last year, NextDecade also revealed plans for carbon capture from the LNG export plant.

The firm expects to capture and store more than five million metric tonnes of CO2 per year.

In November, NextDecade filed a limited amendment to its federal authorization with FERC for the LNG terminal that would allow it to voluntarily capture and store CO2 produced at the facility.

The firm said in the presentation it expects to receive approval from FERC for the CCS project in 2022.

Most Popular

Venture Global to introduce gas to 9th Plaquemines liquefaction block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the ninth liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

Shell’s LNG Canada moving forward with commissioning activities

Shell’s LNG Canada is moving forward with its commissioning and start-up phase and expects to receive a liquefied natural gas (LNG) cargo soon.

Atlantic LNG shipping rates climb to $20,000 per day

Atlantic LNG freight rates rose to almost $20,000 per day this week, while European prices continued to decrease.

More News Like This

NextDecade plans Rio Grande LNG expansion

US LNG firm NextDecade has revealed plans for up to five more trains at its Rio Grande LNG export plant in Texas.

First Rio Grande LNG tank taking shape

US LNG developer NextDecade continues to make progress on the first phase of its Rio Grande LNG export plant in Texas, including the first 180,000-cbm storage tank.

NextDecade gets $175 million loan for Rio Grande LNG

NextDecade's unit Rio Grande LNG Super has entered into a credit agreement with General Atlantic Credit's Atlantic Park Fund...

Construction progresses on NextDecade’s Rio Grande LNG project

Schatzman said in a third-quarter business update that the facility "continues to progress safely, in line with schedule, and...