NextDecade expects Rio Grande LNG FID in second half of 2022

US liquefaction plant developer NextDecade now expects to take a final investment decision to build its proposed Rio Grande LNG export plant in Texas in the second half of 2022.

This means that NextDecade delayed the FID for more than six months as it previously said it had expected to take the decision by the end of 2021.

NextDecade first plans to build two liquefaction trains with a capacity of 11 million tonnes per year. The full project would include five trains with a capacity of 27 mtpa.

However, the firm currently has only a 20-year deal with Shell for 2 mtpa of supplies from the proposed Rio Grande plant.

The company is working to sign new deals with a duration of 10-20 years after it plans to work on the project’s financing, according to NextDecade’s newest investor presentation released on Monday.

NextDecade said SPA negotiations were “advancing with multiple counterparties in Europe and Asia” but it did not provide any additional information.

Bechtel contract

The LNG developer has lump-sum turnkey EPC contracts with engineering giant Bechtel.

Also, the duo completed a pricing refresh in March last year and they expect EPC costs for the first two trains, along with two 180,000-cbm tanks and a jetty, to reach about $7.5 billion. The other three trains and associated infrastructure would cost about $10 billion.

All five trains would use Air Products’ C3MR technology and Baker Hughes’ rotating equipment.

Prior to FID, the partners would need to work on the final EPC contract pricing as the current pricing had expired on December 31, 2021, NextDecade said.

Carbon capture

Last year, NextDecade also revealed plans for carbon capture from the LNG export plant.

The firm expects to capture and store more than five million metric tonnes of CO2 per year.

In November, NextDecade filed a limited amendment to its federal authorization with FERC for the LNG terminal that would allow it to voluntarily capture and store CO2 produced at the facility.

The firm said in the presentation it expects to receive approval from FERC for the CCS project in 2022.

- Advertisements -

Most Popular

Hyundai Samho to build LNG carrier quartet for $1.08 billion

South Korea's Hyundai Samho has secured an order to build four liquefied natural gas (LNG) carriers for about $1.08...

QatarEnergy to further boost LNG output

State-owned LNG giant QatarEnergy said on Sunday it will further boost its liquefied natural gas production from the North...

Tellurian reports $166.2 million net loss in 2023

US LNG firm Tellurian reported a net loss of $166.2 million in 2023, as it continues to work on...

More News Like This

NextDecade enters loan as it works on FID for fourth Rio Grande LNG train

US LNG firm NextDecade has entered into a credit agreement as it works to take a final investment decision...

ABB bags Rio Grande LNG gig

Swiss engineering group ABB has won a contract from Bechtel to provide automation and other solutions for NextDecade’s Rio...

NextDecade plans to take FID on fourth Rio Grande LNG train in H2 2024

US LNG firm NextDecade is planning to take a final investment decision to build the fourth liquefaction train at...

NextDecade officially kicks off Rio Grande LNG work

US LNG firm NextDecade has officially started building the first phase of its Rio Grande LNG export project in...