NextDecade seeks more time to build Rio Grande LNG export plant

NextDecade asked US energy regulators for a two-year extension to construct its proposed Rio Grande LNG export plant in Texas.

In 2019, the company won approval from the US FERC to build the LNG terminal with up to five trains and a total capacity of 27 mtpa by November 22, 2026.

Now, NextDecade is seeking to extend that deadline until November 22, 2028, according to a FERC filing dated April 6.

NextDecade told FERC that Rio Grande LNG was impacted by “unforeseeable developments in the global LNG market as a result of the Covid-19 pandemic, including major disruptions in world energy markets due to a temporary but significant demand destruction resulting from global lock-downs.”

According to the company, the pandemic has affected the ability of Rio Grande LNG to enter into additional long-term offtake contracts with customers sufficient to enable the company to achieve a final investment decision (FID).

More LNG supply contracts to come

However, despite the pandemic, commercialization of Rio Grande LNG has accelerated in the past quarter, NextDecade said.

The company revealed two LNG supply deals with Chinese firms in the last two weeks.

Under the first 20-year HoA announced on March 24, NextDecade would supply up to 1.5 mtpa of LNG indexed to Henry Hub to Guangdong Energy Group Natural Gas.

After that, the Rio Grande developer said it had signed a deal to supply liquefied natural gas to a unit of Chinese independent gas distributor ENN.

Under this 20-year sales and purchase deal, ENN LNG would buy 1.5 mtpa of LNG indexed to Henry Hub on a free-on-board basis.

The LNG supply would come from the first two Rio Grande trains with a capacity of 11 mtpa.

Besides these deals, NextDecade said it expects to execute more contracts over the next quarter.

Following a recent deal, the US will work to supply at least 15 billion cubic meters (bcm) of LNG to European Union markets this year, as the EU looks to slash dependence on Russian gas.

NextDecade said Rio Grande LNG would “play an important role in meeting Europe’s
demand for LNG.”

The company added it anticipates beginning construction and making a positive FID on a minimum of two trains in the second half of 2022.

Most Popular

QatarEnergy CEO says damaged Ras Laffan LNG trains to take three years to repair

State-owned LNG giant QatarEnergy expects the damage to two liquefaction trains at its giant Ras Laffan complex to take three years to repair, according to Qatar’s energy minister and CEO of QatarEnergy, Saad Sherida Al-Kaabi.

Hanwha Ocean, KR to develop LNG bunkering vessel concepts

South Korean shipbuilder Hanwha Ocean is teaming up with Korean Register (KR) to jointly develop two design concepts for an 18,000-cbm LNG bunkering vessel.

Glencore pens Chinese LNG supply deal

Switzerland-based energy trader Glencore has signed a long-term deal to supply liquefied natural gas (LNG) to a unit of China Suntien Green Energy.

More News Like This

Cheniere’s Corpus Christi Trains 8 and 9 project more than 50 percent complete

Cheniere's Corpus Christi Midscale Trains 8 and 9 project in Texas is more than 50 percent complete, according to the latest construction update.

Construction progresses on Woodside’s Louisiana LNG project

Australian LNG player Woodside and its contractor Bechtel continue to advance construction of the first phase of the Louisiana LNG export terminal.

Glenfarne’s Magnolia LNG seals feed gas deal

Glenfarne’s Magnolia LNG has signed a long-term feed gas deal with Texas Eastern Transmission for its planned liquefaction and export plant in Louisiana.

Sterling delivers Rio Grande LNG tug

Texas-based Sterling Shipyard has delivered a tug to a joint venture comprised of Bay-Houston Management, Moran Towing, and Suderman & Young Towing. The new tug will serve NextDecade's Rio Grande LNG project in Texas.