Peru LNG ships first October cargo

Peru LNG has shipped the first liquefied natural gas (LNG) cargo from its plant at Pampa Melchorita in October, according to state-owned Perupetro.

Perupetro’s data shows that the 174,000-cbm LNG carrier GasLog Genoa left Peru LNG’s 4.45 mtpa liquefaction plant on October 7 to Canada.

Its AIS data provided by VesselsValue reveals that the LNG carrier was on Monday near Balboa, Panama City, located at the Pacific entrance to the Panama Canal.

Prior to this shipment, the Peru LNG plant sent cargoes onboard the 138,000-cbm LNG carrier Bilbao Knutsen and the 135,400-cbm Seapeak Madrid in September.

Bilbao Knutsen is on its way to the UK, while Seapeak Madrid is heading towards Spain, Perupetro’s data shows.

Peru LNG shipped three LNG cargoes in August following a planned maintenance shutdown in July.

The plant at Pampa Melchorita shipped five cargoes in June, the same as in the month before.

Issues with feed gas affected LNG shipments from the Peru LNG plant in August and September.

Peru’s energy and mines ministry announced on August 11 an emergency measure to allow it to prioritize domestic natural gas supplies due to reduced supplies from Pluspetrol’s Las Malvinas natural gas plant.

Due to necessary repairs at the plant which feeds the LNG facility, this measure first lasted from August 11 to August 24, but it was extended to September 20 due to additional works.

In total, the LNG plant sent 685 LNG cargoes since 2010, Perupetro’s data shows.

US-based Hunt Oil holds a 50 percent operating stake in the Pampa Melchorita LNG plant, while SK and Marubeni have 20 percent and 10 percent, respectively.

LNG giant Shell also holds a 20 percent stake and takes all the volumes produced at the facility.

Most Popular

Shell adds another LNG carrier to its fleet

A unit of UK-based LNG giant Shell has added another chartered liquefied natural gas carrier to its fleet.

CMA CGM’s LNG-powered giant floated out in China

China’s Hudong-Zhonghua has launched the third in a new series of 24,000-teu LNG dual-fuel containerships for French shipping giant CMA CGM.

Venture Global gets OK to introduce gas to final Plaquemines LNG block

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce natural gas to the 18th and final liquefaction block at the Plaquemines LNG terminal in Louisiana as part of the plant’s commissioning process.

More News Like This

Peru LNG sent five cargoes in July

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in July, the same as in the previous month.

Peru LNG shipped five cargoes in June

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in June, the same as in the previous month.

Peru LNG terminal shipped five cargoes in May

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped five liquefied natural gas cargoes in May, two more than in the previous month.

Peru LNG terminal shipped three cargoes in April