Sempra secures more time to build Port Arthur LNG export plant

US LNG firm Sempra Infrastructure, a unit of Sempra, has secured a 50-month extension from US energy regulators to build its 13.5 mtpa Port Arthur liquefaction project in Texas.

US FERC approved the Port Arthur project back in April 2019 and Sempra had to complete the LNG export terminal and associated pipelines by April 2024.

Port Arthur LNG and Port Arthur Pipeline requested the extension from FERC on July 28 saying the project was impacted by the “adverse market conditions and logistical delays caused by the Covid-19 pandemic”.

“Because we find that Port Arthur has demonstrated good cause for delay and progress in developing the projects, we will grant the requested 50-month extension of time to complete construction of the Port Arthur LNG Terminal and the Louisiana Connector Project and Texas Connector Project,” FERC said in a filling dated October 13.

Following the approval, Sempra Infrastructure now has to construct and make available for service the Port Arthur LNG terminal by June 18, 2028.

The liquefaction project would consist of two liquefaction trains each capable of producing up to 6.73 mtpa. Sempra Infrastructure also plans a similarly sized second phase of the project.

Also, the first phase of the project includes three LNG storage tanks with a capacity of 160,000 cubic meters and a marine facility consisting of two berths for LNG vessels with a capacity of up to 266,000 cbm.

Sempra Infrastructure has entered into negotiations with “multiple European companies that contemplate negotiation of long-term sale and purchase agreements for LNG from the liquefaction project,” the filling said.

Earlier this year, US energy giant ConocoPhillips signed a preliminary deal with Sempra Infrastructure to buy a 30 percent direct equity holding in the project and an LNG offtake equivalent to about 5 mtpa.

Prior to this HOA, Sempra signed deals with German energy firm RWEUK’s Ineos, and Poland’s dominant gas firm and LNG importer, PGNiG, for volumes from the first phase of the LNG project.

Including this deal with ConocoPhillips, these HOAs total 9.65 mtpa to 11.65 mtpa of LNG from the first phase of the development, according to Sempra.

Most Popular

BP, Venture Global to supply LNG to Bulgargaz in January and February

Bulgargaz previously sought two LNG cargoes for delivery during January and February 2025. The company recently announced that 19 international...

Geocean kicks off work on Congo FLNG mooring project

French marine and offshore contractor, Geocean, a VINCI Construction Grands Projets unit, has started working on a new contract...

Petronas, CNPC strengthen LNG ties

Malaysia's Petronas and China National Petroleum Corporation (CNPC) signed a memorandum of understanding (MoU) to strengthen collaboration in various...

More News Like This

Sempra expects non-FTA approval for Port Arthur LNG expansion in H1 2025

Sempra Infrastructure previously won approval from the US FERC for the proposed Phase 2 project, and it also secured the FTA...

Venture Global moving forward with Plaquemines LNG commissioning

The regulator said in a filing dated November 6 that it grated Venture Global Plaquemines LNG's request to commission...

Golden Pass secures three-year extension to complete Texas LNG terminal

Under the original FERC order from 2016, Golden Pass LNG was required to complete and place into service the...

Cheniere’s Corpus Christi expansion project nears launch of LNG production

"Together with Bechtel, we continue to advance our Corpus Christi Stage 3 project ahead of schedule and anticipate achieving...