Sempra secures more time to build Port Arthur LNG export plant

US LNG firm Sempra Infrastructure, a unit of Sempra, has secured a 50-month extension from US energy regulators to build its 13.5 mtpa Port Arthur liquefaction project in Texas.

US FERC approved the Port Arthur project back in April 2019 and Sempra had to complete the LNG export terminal and associated pipelines by April 2024.

Port Arthur LNG and Port Arthur Pipeline requested the extension from FERC on July 28 saying the project was impacted by the “adverse market conditions and logistical delays caused by the Covid-19 pandemic”.

“Because we find that Port Arthur has demonstrated good cause for delay and progress in developing the projects, we will grant the requested 50-month extension of time to complete construction of the Port Arthur LNG Terminal and the Louisiana Connector Project and Texas Connector Project,” FERC said in a filling dated October 13.

Following the approval, Sempra Infrastructure now has to construct and make available for service the Port Arthur LNG terminal by June 18, 2028.

The liquefaction project would consist of two liquefaction trains each capable of producing up to 6.73 mtpa. Sempra Infrastructure also plans a similarly sized second phase of the project.

Also, the first phase of the project includes three LNG storage tanks with a capacity of 160,000 cubic meters and a marine facility consisting of two berths for LNG vessels with a capacity of up to 266,000 cbm.

Sempra Infrastructure has entered into negotiations with “multiple European companies that contemplate negotiation of long-term sale and purchase agreements for LNG from the liquefaction project,” the filling said.

Earlier this year, US energy giant ConocoPhillips signed a preliminary deal with Sempra Infrastructure to buy a 30 percent direct equity holding in the project and an LNG offtake equivalent to about 5 mtpa.

Prior to this HOA, Sempra signed deals with German energy firm RWEUK’s Ineos, and Poland’s dominant gas firm and LNG importer, PGNiG, for volumes from the first phase of the LNG project.

Including this deal with ConocoPhillips, these HOAs total 9.65 mtpa to 11.65 mtpa of LNG from the first phase of the development, according to Sempra.

Most Popular

Woodside names Sarah Bairstow as Louisiana LNG head

Australian LNG player Woodside has appointed Sarah Bairstow to lead its Louisiana LNG project.

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

BP, partners ship first Tortue LNG cargo

UK-based energy giant BP and its partners have shipped the first liquefied natural gas (LNG) cargo produced at the Greater Tortue Ahmeyim FLNG project, located offshore Mauritania and Senegal, according to shipping data.

More News Like This

Cheniere to start site preparation for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere is seeking approval from the US FERC to start site preparation activities for two more midscale trains at its Corpus Christi LNG plant in Texas.

Energy Transfer seeks FERC extension for Lake Charles LNG export terminal

Texas-based Energy Transfer is seeking an extension of time from the US FERC to complete and place into service its planned Lake Charles LNG export facility in Louisiana.

Freeport LNG gets OK to place Noble gas project in service

Freeport LNG, the operator of the 15 mtpa liquefaction plant in Texas, has secured approval from the US FERC to place into service its Noble gas project.

Cheniere progresses commissioning of second Corpus Christi expansion train

US LNG exporting giant Cheniere is moving forward with commissioning activities at the second train of the Corpus Christi Stage 3 expansion project in Texas following the substantial completion of the first unit.