Sempra secures more time to build Port Arthur LNG export plant

US LNG firm Sempra Infrastructure, a unit of Sempra, has secured a 50-month extension from US energy regulators to build its 13.5 mtpa Port Arthur liquefaction project in Texas.

US FERC approved the Port Arthur project back in April 2019 and Sempra had to complete the LNG export terminal and associated pipelines by April 2024.

Port Arthur LNG and Port Arthur Pipeline requested the extension from FERC on July 28 saying the project was impacted by the “adverse market conditions and logistical delays caused by the Covid-19 pandemic”.

“Because we find that Port Arthur has demonstrated good cause for delay and progress in developing the projects, we will grant the requested 50-month extension of time to complete construction of the Port Arthur LNG Terminal and the Louisiana Connector Project and Texas Connector Project,” FERC said in a filling dated October 13.

Following the approval, Sempra Infrastructure now has to construct and make available for service the Port Arthur LNG terminal by June 18, 2028.

The liquefaction project would consist of two liquefaction trains each capable of producing up to 6.73 mtpa. Sempra Infrastructure also plans a similarly sized second phase of the project.

Also, the first phase of the project includes three LNG storage tanks with a capacity of 160,000 cubic meters and a marine facility consisting of two berths for LNG vessels with a capacity of up to 266,000 cbm.

Sempra Infrastructure has entered into negotiations with “multiple European companies that contemplate negotiation of long-term sale and purchase agreements for LNG from the liquefaction project,” the filling said.

Earlier this year, US energy giant ConocoPhillips signed a preliminary deal with Sempra Infrastructure to buy a 30 percent direct equity holding in the project and an LNG offtake equivalent to about 5 mtpa.

Prior to this HOA, Sempra signed deals with German energy firm RWEUK’s Ineos, and Poland’s dominant gas firm and LNG importer, PGNiG, for volumes from the first phase of the LNG project.

Including this deal with ConocoPhillips, these HOAs total 9.65 mtpa to 11.65 mtpa of LNG from the first phase of the development, according to Sempra.

Most Popular

Japan’s Tokyo Gas to expand LNG trading business

Japan’s city gas supplier and LNG importer, Tokyo Gas, plans to expand its liquefied natural gas trading business further, including in the US.

Shell CEO expects progress on Venture Global arbitration this year

Shell’s CEO Wael Sawan expects to have an update on an arbitration dispute with US LNG exporter Venture Global LNG later this year.

China’s SIPG eyes LNG bunkering vessel order

China’s terminal operator, Shanghai International Port (SIPG), is looking to order one large liquefied natural gas (LNG) bunkering vessel, according to shipbuilding sources.

More News Like This

Venture Global LNG seeks Calcasieu Pass approval from FERC

US LNG exporter Venture Global LNG is seeking approval from the US FERC to launch operations of its entire Calcasieu Pass LNG terminal in Louisiana.

NextDecade: US court revises FERC’s order for Rio Grande LNG

US LNG firm NextDecade said that the US Court of Appeals for the District of Columbia had revised its August 2024 judgment against the Federal Energy Regulatory Commission’s order for the first five liquefaction trains at the Rio Grande LNG facility in Texas.

Cheniere gets FERC OK for two more Corpus Christi LNG trains

US LNG exporting giant Cheniere has received approval from the US FERC to build two more midscale trains at its Corpus Christi LNG plant in Texas.

NextDecade plans Rio Grande LNG expansion

US LNG firm NextDecade has revealed plans for up to five more trains at its Rio Grande LNG export plant in Texas.