Sempra seeks FERC approval for revised Cameron LNG expansion plans

LNG operator and energy firm Sempra asked US energy regulators to approve its revised expansion plans for the Cameron LNG export plant in Louisiana.

Sempra indirectly holds 50.2 percent of Cameron LNG, the operator of the three-train 12 mtpa liquefaction facility. Other partners include affiliates of TotalEnergies, Mitsui & Co, and Japan LNG Investment, a company held by Mitsubishi Corp and NYK.

Besides these three trains, Sempra and its partners planned to build two additional LNG units, adding about 10 mtpa.

However, Sempra said last year that the partners changed their original plans and aim to build only the fourth train with a capacity of about 6 mtpa.

In a filing this week, Cameron LNG asked the US FERC to approve these amended plans.

Cameron LNG submitted the application for a limited amendment to the existing authorization issued by FERC on May 5, 2016, which included, among others, two trains with a total capacity of 9.97 million tonnes.

“Cameron LNG is proposing in this amendment application to implement several design modifications and enhancements to reduce the overall greenhouse gas emissions from the project, allow for Cameron LNG to gain access to carbon capture and storage facilities in the future, and to enhance the overall efficiency and productive capacity of the expansion project,” it said.

Electric turbines

The proposed amendment will include one liquefaction train with a maximum LNG production capacity of 6.75 mtpa with its own feed gas pretreatment facility.

Also, the design enhancements of the fourth train would include the use of an electric drive (E-Drive) motor to replace the Frame 7 gas turbine drives, and tie-ins to allow optionality of carbon sequestration of the acid gas from the unit, Cameron LNG said.

The firm is proposing to replace its primary gas-driven turbines with an E-Drive technology that utilizes power sourced from the local utility, Entergy.

Cameron LNG said this would make it one of only two LNG facilities in North America, besides Freeport LNG, to utilize this technology.

“The use of this technology will reduce by approximately 44 percent the overall onsite
emissions from Train 4 from 1,840,740 tons per year of CO2 equivalent gas to 1,030,152 tpy of CO2e,” it said.

In addition, the amended expansion project would preserve the “opportunity for the terminal to take advantage of the possible CCS infrastructure in the Gulf Coast, if and when such infrastructure is developed and assuming it is accessible to Cameron LNG both logistically and economically,” it said.

Cameron LNG said the design enhancements relate solely to equipment associated with Train 4 and do not alter or impact the existing marine facilities at the plant.

The firm would also not build the fifth LNG tank associated with the fifth train.

Cameron LNG estimates a total economic impact resulting from construction of the expansion project of $2.2 billion.

According to Cameron LNG, if FERC approves the application by January 2023, the terminal operator could start construction in April of the same year and launch the expansion in the third quarter of 2027.

Most Popular

Singfar orders LNG bunkering duo in China

Singapore-based shipowner Singfar has ordered two large LNG bunkering vessels from China's Huangpu Wenchong Shipbuilding.

Precious Shipping’s new Malaysian JV targets LNG and LPG carriers

Precious Shipping's new Malaysian joint venture with Emstraits Navigation and Lianson Fleet Group will be looking to acquire liquefied natural gas (LNG), liquefied petroleum gas (LPG), and crude tankers.

Noatum Maritime welcomes first LNG-powered PCTC in its fleet

AD Ports Group’s Noatum Maritime has taken delivery of its first LNG-powered pure car and truck carrier (PCTC).

More News Like This

Sempra sees potential for 90 mtpa LNG export portfolio

Sempra Infrastructure, a unit of Sempra, sees a potential to build an LNG export portfolio in the US and Mexico of up to 90 million tonnes per annum, according to Justin Bird, CEO of Sempra Infrastructure.

Sempra eyes Port Arthur LNG expansion FID in 2025

Sempra Infrastructure, a unit of Sempra, expects to make a final investment decision on the second phase of its Port Arthur LNG export project in Texas in 2025.

US DOE releases LNG export study

The Biden administration said in January it will pause pending decisions on exports of LNG to non-FTA countries until DOE can...

Construction advances on Sempra’s Port Arthur LNG export terminal

In March last year, Sempra Infrastructure, a unit of Sempra, took a final investment decision for the first phase of its...