Tellurian says Driftwood LNG early works progress

US LNG firm Tellurian continues to progress with site preparation works for its Driftwood LNG export project in Louisiana.

In March, Tellurian issued a limited notice to proceed to US engineering and construction giant Bechtel under its executed EPC contract to begin construction of phase one of the Driftwood LNG plant.

Phase one will include two LNG plants near Lake Charles with an export capacity of up to 11 million tonnes per annum (mtpa).

Tellurian already signed three 10-year LNG supply deals for the Driftwood project for a total of 9 mtpa. These include contracts with Gunvor, Vitol, and Shell.

The firm is still working to complete financing for the project.

Tellurian updates on Driftwood LNG early works
Concrete pile staging area established (Image: Tellurian)

Pile driving

The LNG terminal developer said in its June construction report sent to US FERC that the project continued activities under the LNTP scope.

These include site preparation, the completion of aboveground demolition of the major buildings, mobilization of construction equipment and tools, and preparations for concrete pile driving scheduled for July 2022.

On June 21, FERC issued approval of Driftwood LNG’s pile driving noise management plan.

In addition, Driftwood LNG won approval for its variance request No. 1 to prepare an additional temporary workspace to facilitate deliveries and storage of construction material via existing roads and the existing barge slip that provides direct access to the Calcasieu Ship Channel.

Upstream boost and $750 million invested in Driftwood LNG

Tellurian recently purchased natural gas assets in the Haynesville Shale for about $125 million, as part of plans to boost its upstream position.

Moreover, the firm’s co-founder and executive chairman, Charif Souki, said that the firm had invested $750 million in its Driftwood project in Louisiana up to date.

He said the firm has committed to spend another $250 million with Bechtel for Driftwood for the rest of of the year.

Souki also said that Tellurian “is still on schedule” to deliver LNG in the first quarter of 2026, adding that the financing “will fall into in place in the proper order”.

According to the company’s latest corporate presentation, it now expects costs for the first Driftwood phase to reach $12.8 billion.

Most Popular

Venture Global gets FERC OK to boost Calcasieu Pass LNG capacity

US LNG exporter Venture Global LNG has received approval from the US FERC to increase the peak liquefaction capacity of its Calcasieu Pass LNG terminal in Louisiana.

Worley updates on CP2 LNG work

Australian engineering firm Worley has provided an update on its reimbursable EPC contract with US LNG exporter Venture Global LNG for the latter's CP2 LNG terminal in Louisiana.

Santos gets $18.7 billion takeover offer from Adnoc-led consortium

Australian LNG player Santos has received a takeover offer valued at $18.7 billion from a consortium led by Adnoc's investment unit XRG.

More News Like This

Woodside’s Louisiana LNG gets FERC extension

Woodside has secured an additional eight-month extension from the US FERC to complete and put into service its Louisiana LNG export facility.

Woodside’s Louisiana LNG seeks FERC extension

Woodside is seeking an additional eight-month extension from the US FERC to complete and put into service its Louisiana LNG export facility.

Aramco plans to join Woodside’s Louisiana LNG project

Saudi Arabia’s energy behemoth Aramco plans to take a stake in Woodside's Louisiana LNG export project.

Wood bags Louisana LNG pipeline gig from Woodside

UK-based consulting and engineering firm Wood has secured a contract from Australian LNG player Woodside for the latter's Line 200 pipeline project, which will deliver natural gas to the recently approved Louisiana LNG project.