Tellurian says Driftwood LNG early works progress

US LNG firm Tellurian continues to progress with site preparation works for its Driftwood LNG export project in Louisiana.

In March, Tellurian issued a limited notice to proceed to US engineering and construction giant Bechtel under its executed EPC contract to begin construction of phase one of the Driftwood LNG plant.

Phase one will include two LNG plants near Lake Charles with an export capacity of up to 11 million tonnes per annum (mtpa).

Tellurian already signed three 10-year LNG supply deals for the Driftwood project for a total of 9 mtpa. These include contracts with Gunvor, Vitol, and Shell.

The firm is still working to complete financing for the project.

Tellurian updates on Driftwood LNG early works
Concrete pile staging area established (Image: Tellurian)

Pile driving

The LNG terminal developer said in its June construction report sent to US FERC that the project continued activities under the LNTP scope.

These include site preparation, the completion of aboveground demolition of the major buildings, mobilization of construction equipment and tools, and preparations for concrete pile driving scheduled for July 2022.

On June 21, FERC issued approval of Driftwood LNG’s pile driving noise management plan.

In addition, Driftwood LNG won approval for its variance request No. 1 to prepare an additional temporary workspace to facilitate deliveries and storage of construction material via existing roads and the existing barge slip that provides direct access to the Calcasieu Ship Channel.

Upstream boost and $750 million invested in Driftwood LNG

Tellurian recently purchased natural gas assets in the Haynesville Shale for about $125 million, as part of plans to boost its upstream position.

Moreover, the firm’s co-founder and executive chairman, Charif Souki, said that the firm had invested $750 million in its Driftwood project in Louisiana up to date.

He said the firm has committed to spend another $250 million with Bechtel for Driftwood for the rest of of the year.

Souki also said that Tellurian “is still on schedule” to deliver LNG in the first quarter of 2026, adding that the financing “will fall into in place in the proper order”.

According to the company’s latest corporate presentation, it now expects costs for the first Driftwood phase to reach $12.8 billion.

Most Popular

Delfin takes FID on first FLNG

Delfin Midstream has taken a final investment decision for the first 4.4 mtpa floating liquefied natural gas unit of its LNG project under development in Louisiana. Delfin says the FLNG is the first floating liquefaction facility in the United States and the world's largest FLNG.

Malaysia’s Petronas Gas, Integrax ink pact for new LNG import terminal

Malaysia's Petronas Gas, a unit of Petronas, has signed a binding deal with compatriot Integrax, a part of TNB Power Generation, to jointly develop the country's first FSRU-based LNG import terminal in Lumut, Perak.

Cook Inlet LNG seeks OK to start pre-filing process for Alaska FSRU project

Cook Inlet LNG, a unit of Louisiana-based Gardes Holdings, is seeking approval from the US FERC to initiate the pre-filing process for its planned FSRU-based LNG import project in Alaska's Cook Inlet.

More News Like This

Woodside awards Louisiana LNG tugboat contract

Australian LNG player Woodside has awarded a services contract to Green Tug Towing, a joint venture of Harbor Docking & Towing and Saltchuk Marine, for the design and construction of four new tugs to be built at C&C Marine and Repair in Louisiana, and delivered to Louisiana LNG in 2028.

CCEC names Martin Houston as chairman

LNG carrier owner Capital Clean Energy Carriers (CCEC) has appointed Martin Houston, former chief operating officer of BG and co-founder of Tellurian, as its chairman.

Woodside sees strong interest in further Louisiana LNG sell-downs

Australian LNG player Woodside sees strong interest from counterparties to sell down further equity in its three-train Louisiana LNG export plant, according to acting CEO Liz Westcott.

Woodside seeks more Louisiana LNG partners, including for expansion

Australian LNG player Woodside wants to sell down further equity in its three-train Louisiana LNG export plant. At the same time, the firm also wants to have a partner or partners lined up for trains four and five before it pulls the trigger on a final investment decision on the expansion project, according to CEO Meg O’Neill.