Tellurian updates on Driftwood LNG early works

US LNG firm Tellurian and compatriot engineering and construction giant Bechtel are moving forward with site preparation works for the Driftwood LNG export project in Louisiana.

In March, Tellurian issued a limited notice to proceed to Bechtel under its executed EPC contract to begin construction of phase one of the Driftwood LNG plant.

Tellurian is still working to complete financing for the project worth about $12.8 billion.

Phase one will include two LNG plants near Lake Charles with an export capacity of up to 11 million tonnes per annum (mtpa).

The LNG terminal developer said in its July construction report sent to US FERC that the project continued activities under the LNTP scope.

These include site preparation, concrete pile driving, offloading of concrete pile shipments,
mobilization of construction equipment and tools, and preparations to commence
concrete crushing scheduled for August, according to the update.

Tellurian updates on Driftwood LNG early works
Pile laydown area (Image: Tellurian)

In addition, Driftwood LNG continued the construction of the water wells as a non-jurisdictional activity under the early works program, it said.

In August, Tellurian and Bechtel will continue mobilizing professional staff and craft professionals and will continue demolition of building foundations and underground utilities.

They will also start stripping and site preparation in the LNG tanks area as well as begin receiving rebar for permanent plant foundations.

Tellurian’s co-founder and executive chairman, Charif Souki, said in June that the firm invested $750 million in its Driftwood project in Louisiana up to date.

He said the firm committed to spend another $250 million with Bechtel for Driftwood for the rest of of the year.

Souki also said that Tellurian “is still on schedule” to deliver LNG in the first quarter of 2026, adding that the financing “will fall into in place in the proper order”.

Most Popular

LNG carrier anchors offshore Germany’s Mukran after grounding

The 138,000-cbm LNG carrier Iberica Knutsen was on Friday anchored offshore Mukran, the home of the Deutsche ReGas-operated FSRU-based LNG import facility, following a grounding incident. Deutsche ReGas told LNG Prime that unloading of the vessel's LNG cargo is "part of ongoing operational planning."

Venture Global to start CP2 LNG construction after FERC approval

US LNG exporter Venture Global LNG plans to start construction of its CP2 LNG project in Louisiana "immediately" following approval from the US FERC.

Vopak in advanced talks to secure FSRU for Australian LNG import project

Dutch independent storage tank firm Vopak said it is in advanced talks to secure a converted floating storage and regasification unit for its planned LNG import facility in Australia’s Victoria state.

More News Like This

Woodside’s Louisiana LNG seeks FERC extension

Woodside is seeking an additional eight-month extension from the US FERC to complete and put into service its Louisiana LNG export facility.

Aramco plans to join Woodside’s Louisiana LNG project

Saudi Arabia’s energy behemoth Aramco plans to take a stake in Woodside's Louisiana LNG export project.

Wood bags Louisana LNG pipeline gig from Woodside

UK-based consulting and engineering firm Wood has secured a contract from Australian LNG player Woodside for the latter's Line 200 pipeline project, which will deliver natural gas to the recently approved Louisiana LNG project.

BP to supply feed gas to Woodside’s Louisiana LNG

UK-based energy giant BP has agreed to supply feed gas to Woodside's three-train, 16.5 mtpa Louisiana LNG export project.