Tellurian working with Baker Hughes to secure Driftwood LNG equipment

US LNG terminal developer Tellurian is working with compatriot energy services firm Baker Hughes to secure long-lead items for its Driftwood LNG project, while engineering and construction giant Bechtel continues to progress initial work at the site in Louisiana.

Tellurian issued a limited notice to proceed to Bechtel in March last year. Bechtel has driven over 9,000 piles and poured over 10,000 cubic feet of concrete for plant one and the storage tanks since then.

The Houston-based firm is expecting the development costs for the first phase of its Driftwood LNG export plant to reach $14.5 billion and the company is still working to secure financing for the project.

Under the first phase, Tellurian aims to build two LNG plants near Lake Charles with an export capacity of up to 11 mtpa.

Tellurian’s co-founder and executive chairman, Charif Souki said in a video update last week after the company’s second-quarter results that the company’s focus lately has been on two areas.

“The first is Driftwood LNG, where we continue to drive piles with Bechtel and continue to build the foundation,” he said.

“And that effort will continue with the second notice to proceed for the balance of this year and half of next year and we’ll prepare the site for the final notice to proceed,” he said.

Tellurian to spend $1.5 billion on Driftwood

Souki said that the “next step forward on Driftwood is to start securing long-lead items, mainly the turbines and the compressors that have been so important to both the the airline industry and the LNG industry.”

“And given all the recent orders for turbines, it is important to continue to secure our place in the queue to secure these facilities on time,” he said.

Souki said that Tellurian has spent up to date $16 million dollars securing the turbine purchases and will continue to work with Baker Hughes for these deliveries.

“So look for more news on that,” he said.

“When we finalize this, we will have spent $1.5 billion on Driftwood to prepare it for the final notice to proceed,” he said.

Soki said that Tellurian’s investment into the Drfitwood project continues to increase, “making our proposition to our partners increasingly compelling because a lot of the work has been done and a lot of the risk has been taken out of the picture.”

“I’ve said this before and I will repeat it again here, we will do the right deal for our shareholders,” he said.

Gunvor deal terminated, commissioning LNG cargoes for financing

Tellurian recently said that its LNG supply deal with trader Gunvor was terminated.

This was the only LNG supply deal Tellurian had for the planned Driftwood LNG project after both of its LNG supply deals with Shell and Vitol fell through.

Back in May 2021, Tellurian agreed to supply 3 million tonnes per annum on a free on board (FOB) basis to Gunvor Singapore for a period of 10 years.

As part of its financing strategy, Tellurian entered last month into a binding commitment letter with a fund of Blue Owl Real Estate Capital regarding the sale and leaseback of Driftwood land.

According to Tellurian’s latest corporate presentation posted on its website, the Driftwood capital structure includes $7 billion bank debt, $2 billion lease/mezzanine financing, $1.8 billion partner equity, $1.5 billion Tellurian equity, and also $2.5 billion contingent equity.

If the six months of commissioning LNG cargoes cover the contingent equity, the contingent equity will not be funded, according to Tellurian.

This is probably the first time Tellurian mentioned that commissioning LNG cargoes could cover part of Driftwood financing.

Tellurian added it is seeking partners to invest 55 percent of the equity for 6 mtpa capacity in the first phase of the project.

- Advertisements -

Most Popular

QatarEnergy seals major deal with Chinese shipbuilder for 18 Q-Max LNG carriers

State-owned LNG giant QatarEnergy has signed a major shipbuilding deal with China State Shipbuilding Corp for the construction of...

TotalEnergies CEO: Mozambique LNG restart is not a matter of costs

French energy giant TotalEnergies had "good" discussions with Mozambique LNG contractors and they agreed not to inflate the costs...

Spot LNG shipping rates, European prices drop this week

Spot charter rates for the global liquefied natural gas (LNG) carrier fleet dropped slightly this week, while European and...

More News Like This

Baker Hughes won $200 million in LNG equipment orders in Q1

US energy services firm Baker Hughes booked about $200 million of LNG equipment orders in the first quarter of...

Woodside: largest compressor module arrives at Pluto Train 2 site

Australian LNG producer Woodside has received the largest compressor module from Indonesia at the Pluto Train 2 project site...

Baker Hughes to supply liquefaction tech for Canada’s Cedar LNG project

US energy services firm Baker Hughes has secured an order from compatriot engineer Black & Veatch to supply the...

Work progresses on NextDecade’s Rio Grande LNG export plant in Texas

US LNG firm NextDecade is moving forward with construction work on the first phase of its Rio Grande LNG...