Venture Global gets OK to commission 8th block at Calcasieu Pass LNG plant

US LNG export player Venture Global LNG has received approval from federal regulators to start commissioning the Block 8 liquefaction modules at its Calcasieu Pass plant in Louisiana.

The Federal Energy Regulatory Commission (FERC) said in a filing dated May 27 it had approved Venture Global’s recent request to launch the Block 8 liquefaction modules.

Earlier this month, Venture Global said it was seeking approval to put in service the first four liquefaction blocks at the facility.

FERC approved this on May 13, according to a filling.

To remind, Calcasieu Pass produced its first LNG on January 19 and shipped the first commissioning cargo on March 1.

Following completion, the project will have a capacity to produce 10 mtpa of LNG or 1.3 billion cubic feet per day (Bcf/d) from 18 modular units configured in 9 blocks.

The US Energy Information Administration expects Venture Global LNG’s Calcasieu Pass liquefaction plant to reach full production by the third quarter of this year.

Most of Calcasieu Pass commissioning cargoes arrived in Europe due to high prices and as the continent looks to reduce reliance on Russian gas supplies.

The Calcasieu Pass project is the seventh US liquefaction and export facility to begin producing LNG since 2016.

It receives its feedgas through Venture Global’s TransCameron pipeline, which has interconnections with the ANR, TETCO, and Bridgeline pipelines.

The project has contracts with Shell, BP, Edison, Galp, Repsol, PGNiG, Sinopec’s unit Unipec, and CNOOC.

Besides this plant, Venture Global recently announced it had taken a final investment decision for the 13.33 mtpa Plaquemines LNG project and the related pipeline after it secured $13.2 billion in project financing.

This is the first LNG project located in the US to reach financial close since Venture Global’s Calcasieu Pass facility in August 2019.

Most Popular

Petronet expects to launch additional Dahej LNG capacity by June

The Dahej LNG terminal is India's largest LNG import facility and currently has a capacity of 17,5 mtpa. Last year,...

Gastrade: Alexandroupolis FSRU remains offline due to technical issue

"For the moment, regasification services have been suspended due to a technical issue, for which we will provide further...

China to impose tariff on US LNG

China's Ministry of Finance said in a statement on Tuesday that the US government announced on February 1 the...

More News Like This

Venture Global LNG awards contracts to Baker Hughes

Baker Hughes has been awarded a "major" contract to provide a modularized LNG system and power island to support...

FERC: Venture Global nears completion of Calcasieu Pass LNG repairs

Calcasieu Pass produced its first LNG on January 19, 2022, moving from FID to LNG production in 29 months, and the first...

Venture Global gets OK to introduce gas to seventh Plaquemines liquefaction block

The US FERC approved Venture Global Plaquemines LNG’s request from January 22 to commission and introduce hazardous fluids to...

Germany to receive third Plaquemines LNG cargo

The 2021-built 174,000-cbm, Isabella, was on Tuesday anchored in the North Sea, offshore Wilhelmshaven and Brunsbüttel, where DET’s FSRU-based...