Venture Global preparing Plaquemines LNG site ahead of FID

US firm Venture Global LNG said it has started works to prepare the construction site for its planned Plaquemines LNG project in Louisiana.

“Plaquemines LNG began construction on the terminal site on August 18, 2021,” Venture Global LNG’s unit and the developer of the plant said in its monthly construction report sent to US regulators.

Work consisted of improving the existing driveway, installing the silt fence perimeter, and site mowing, according to the report dated September 7.

However, the firm had to stop these activities on August 27 as Hurricane Ida approached the Louisiana coast west of the site. The hurricane made landfall two days later, bringing heavy rainfall to the terminal site, it said.

“Work will not resume until early September when terminal site conditions improve,” the report said.

Plaquemines LNG would deploy Venture Global’s liquefaction trains 19 through 36, identical to the 18 trains currently being delivered and installed at Venture Global’s Calcasieu Pass project.

The full project would have 20 mtpa capacity, four tanks, and three jetties.

However, the firm has still to take a final investment decision on the development.

According to Venture Global’s website, the firm plans to take a final investment decision on Plaquemines LNG in the fourth quarter of this year. Commercial operations could start in 2024.

Earlier this year, Venture Global said compatriot Zachry Group has joined KBR to build its Plaquemines LNG project.

The firm selected engineer KBR as the lead contractor for the LNG export development in November last year.

Additionally, Plaquemines LNG has binding 20-year offtake agreements with Poland’s PGNiG for 4 mtpa and France’s EDF for 1 mtpa capacity.

Venture Global has recently signed a deal with PGNiG to boost the volumes from both the Plaquemines and the Calcasieu Pass projects.

Most Popular

Venture Global seals new deals to support expansion of its power network

US LNG exporter Venture Global has entered into power and grid frame agreements with GE Vernova and Baker Hughes for up to 16 new, 720 MW power island units and associated power transformer equipment, supporting the continued expansion of its existing behind-the-meter, industrial power network that is not reliant on the grid.

Venture Global gets approval to place first Plaquemines LNG phase in service

Venture Global’s Plaquemines LNG has secured approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

Hanwha Ocean, Posco plan to build LNG carrier with high-manganese steel tanks

South Korean shipbuilder Hanwha Ocean and steel producer Posco plan to build a liquefied natural gas (LNG) carrier equipped with high-manganese steel cargo tanks.

More News Like This

Venture Global gets approval to place first Plaquemines LNG phase in service

Venture Global’s Plaquemines LNG has secured approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

Venture Global seals new deals to support expansion of its power network

US LNG exporter Venture Global has entered into power and grid frame agreements with GE Vernova and Baker Hughes for up to 16 new, 720 MW power island units and associated power transformer equipment, supporting the continued expansion of its existing behind-the-meter, industrial power network that is not reliant on the grid.

Galp wins Calcasieu Pass arbitration against Venture Global

Portuguese energy firm Galp has won an arbitration case against US LNG exporter Venture Global LNG over LNG sales from the Calcasieu Pass plant in Louisiana.

Venture Global shipped 124 LNG cargoes in Q3

US LNG exporter Venture Global shipped 124 LNG cargoes from its Calcasieu Pass and Plaquemines LNG export terminals in the third quarter of this year.