Venture Global to produce first LNG at Calcasieu Pass terminal

Venture Global LNG has received approval from federal regulators to start commissioning a part of its Calcasieu Pass liquefaction plant in Louisiana.

The Federal Energy Regulatory Commission (FERC) approved Venture Global’s recent request to start commissioning the Block 1 liquefaction modules and the south LNG tank.

Once completed, Calcasieu Pass will produce about 10 mtpa of LNG from 18 modular units configured in 9 blocks.

Venture Global previously received approvals from FERC to introduce feed gas to the gas turbine generators, as well as to supply liquid nitrogen to the air separation unit.

The next major step is to introduce feed gas to the liquefaction units.

Venture Global gets Calcasieu Pass modular trains from Baker Hughes’ manufacturing facility in Italy.

The firm said earlier this year that it could start first exports from the LNG facility by the end of this year, with full operations planned in 2022.

Following completion, the Calcasieu Pass project will become the seventh large LNG export facility in the US.

The approval follows a huge LNG supply deal Venture Global has signed with China’s Sinopec worth more than $30 billion, which also includes volumes from Calcasieu Pass.

Venture Global has signed two 20-year sales and purchase agreements for the supply of a total of 4 million tonnes per annum of LNG from its Plaquemines LNG export facility Louisiana.

In addition, Unipec, a Sinopec subsidiary has agreed to purchase 3.5 million tonnes of LNG
from Venture Global’s Calcasieu Pass LNG facility for a shorter duration, it said.

Most Popular

Galp wins Calcasieu Pass arbitration against Venture Global

Portuguese energy firm Galp has won an arbitration case against US LNG exporter Venture Global LNG over LNG sales from the Calcasieu Pass plant in Louisiana.

Seatrium scores Excelerate FSRU conversion gig

Singapore's Seatrium has secured a floating storage and regasification unit conversion contract with an option for a second contract from US FSRU player Excelerate Energy.

MISC to order five more LNG carriers for Petronas charter

Malaysian shipping firm MISC will order five additional newbuild 174,000-cbm liquefied natural gas (LNG) carriers at China's Hudong-Zhonghua. The vessels will serve a 20-year charter with a unit of MISC's parent, Petronas.

More News Like This

Galp wins Calcasieu Pass arbitration against Venture Global

Portuguese energy firm Galp has won an arbitration case against US LNG exporter Venture Global LNG over LNG sales from the Calcasieu Pass plant in Louisiana.

Venture Global shipped 124 LNG cargoes in Q3

US LNG exporter Venture Global shipped 124 LNG cargoes from its Calcasieu Pass and Plaquemines LNG export terminals in the third quarter of this year.

Venture Global seeks FERC OK to place first Plaquemines LNG phase in service

Venture Global's Plaquemines LNG is seeking approval from the US FERC to place Phase 1 of its LNG export plant in Louisiana into service.

Venture Global, ConocoPhillips seal 20-year LNG SPA

US LNG exporter Venture Global LNG has signed a 20-year LNG sales and purchase deal with compatriot energy giant ConocoPhillips.