India’s Adani and France’s TotalEnergies have almost completed their Dhamra LNG import facility located in Odisha, on India’s east coast.

This was revealed on Wednesday in a social media post by Total Adani, a 50/50 joint venture between the the two firms and the owner of the Dhamra LNG terminal.

ATPL and Dhamra LNG CEO, SatinderPal Singh, visited the Dhamra LNG terminal earlier this week to plan for commissioning of the new facility.

He also inspected the last remaining section of the interconnecting Dhamra-Angul pipeline built by state-owned GAIL, Total Adani said.

“We are days away from achieving mechanical completion of this historic LNG and gas infrastructure that will fill a critical gap in eastern India,” the JV said.

Dhamra LNG to become seventh operation terminal in India

A unit of TotalEnergies said in February last year that the facility was more than 70 percent complete as of December 2020.

Construction of the facility started back in 2018, with India’s Larsen & Toubro responsible for setting up the LNG tanks while Taiwan’s CTCI Corporation won the contract for the regasification package.

Designed for a capacity of 5 mtpa, the Dhamra terminal features two tanks of 180,000 cbm capacity, each. There is a potential to double the capacity to 10 mtpa.

In addition, the terminal’s jetty will be capable of receiving the world’s largest LNG carriers but also reloading smaller vessels. TotalEnergies and Adani also plan to distribute LNG via trucks to the region.

As per capacity takers, the JV entered into 20-year LNG regasification agreements with state-owned Indian Oil Corporation (IOC) and GAIL.

Following completion, this would be the seventh operational LNG terminal in India and second on the east coast.

At the moment, India imports LNG via six facilities with a combined capacity of about 42.7 million tonnes.

These include Petronet LNG’s Dahej and Kochi terminals and Shell’s Hazira terminal.

Most Popular

Venture Global’s Plaquemines LNG to commission third jetty

US LNG exporter Venture Global LNG has received approval from the US FERC to introduce hazardous fluids to the third jetty at its Plaquemines LNG export plant in Louisiana.

Another FSRU arrives in Egypt

The 160,000-cbm FSRU Energos Eskimo has arrived in Egypt from Jordan, according to shipping data. The unit is one of four FSRUs that will serve a charter deal with Egypt's EGAS as the country seeks to meet its growing demand for natural gas.

MOL’s LNG carrier to feature SOFC tech

Japan's MOL and South Korea's Samsung Heavy Industries have received approval from classification society LR for the design of a 174,000-cbm LNG carrier integrating solid oxide fuel fell (SOFC) technology.

More News Like This

TotalEnergies seals Ksi Lisims LNG deal

French energy giant TotalEnergies has signed a 20-year deal with Ksi Lisims LNG to buy LNG from the latter's planned export project in Canada. In addition, TotalEnergies will acquire a 5 percent stake in Houston-based Western LNG, the developer, shareholder, and future operator of the Ksi Lisims LNG project.

TotalEnergies targets Mozambique LNG restart by mid-year, CEO says

France's TotalEnergies and its partners in the giant Mozambique LNG project are planning to restart construction on the 12.8 mtpa project by the middle of this year, according to Patrick Pouyanne, CEO of TotalEnergies.

Three Marsa LNG contracts awarded in Oman

Three firms have secured contracts for the TotalEnergies-led Marsa LNG bunkering project worth about $1.6 billion, according to Oman's Sohar Port and Freezone.

TotalEnergies quarterly LNG earnings up, sales down

French energy giant TotalEnergies reported higher LNG earnings and lower sales in the first quarter of 2025.