Australia’s CIMIC to pay about $365 million to settle Ichthys LNG dispute

Australian contractor CIMIC said it has agreed to pay A$492.5 million ($365 million) to settle a dispute with JKC Australia over construction work at the Inpex-operated Ichthys LNG export project near Darwin.

UGL, bought by CIMIC in 2016, together with its consortium partners CH2M Hill Australia and General Electric won a deal back in 2012 from Icthys EPC contractor JKC Australia.

JKC is a joint venture consisting of JGC, which has a 40 percent share, and KBR and Chiyoda each with a 30 percent share.

The works included design, construction, and commissioning of a combined cycle power plant for the Ichthys LNG project.

In January 2017, the consortium terminated the contract and subsequently commenced arbitration.

CIMIC said in a statement on Tuesday that the arbitration hearings in respect of the termination of the contract were scheduled to begin on April 14.

However, CIMIC said that it has entered into a conditional, confidential commercial agreement with its consortium partners and JKC resulting in a full and final settlement of all matters in connection with the contract.

Under the deal, CIMIC would pay A$192.5 million in April 2022, and an amount of A$300 million in March 2023, as its contribution to the settlement amounts, it said.

Deal remains subject to conditions

The settlement deal remains subject to a number of conditions precedent related primarily to payment obligations. The arbitration will continue until the completion of these conditions.

CIMC expects these to complete this month.

In October last year, Japan’s Inpex, the operator of the Ichthys LNG development, said it has resolved a legal dispute with the project’s EPC contractor JKC.

JKC won the design and construction contract worth about $15 billion back in 2012 to build the 8.9 mtpa LNG plant at Bladin Point near Darwin.

The contractor has completed and delivered the facility in 2018.

Ichthys LNG is a joint venture between operator Inpex and major partner France’s TotalEnergies.

Other partners include Australian units of CPC Corporation Taiwan, Tokyo Gas, Osaka Gas, Kansai Electric Power but also JERA and Toho Gas.

Most Popular

Delfin takes FID on first FLNG

Delfin Midstream has taken a final investment decision for the first 4.4 mtpa floating liquefied natural gas unit of its LNG project under development in Louisiana. Delfin says the FLNG is the first floating liquefaction facility in the United States and the world's largest FLNG.

Malaysia’s Petronas Gas, Integrax ink pact for new LNG import terminal

Malaysia's Petronas Gas, a unit of Petronas, has signed a binding deal with compatriot Integrax, a part of TNB Power Generation, to jointly develop the country's first FSRU-based LNG import terminal in Lumut, Perak.

Cook Inlet LNG seeks OK to start pre-filing process for Alaska FSRU project

Cook Inlet LNG, a unit of Louisiana-based Gardes Holdings, is seeking approval from the US FERC to initiate the pre-filing process for its planned FSRU-based LNG import project in Alaska's Cook Inlet.

More News Like This

Ichthys LNG workers start strike

Workers at the Inpex-operated Ichthys ​liquefied natural gas (LNG) export terminal in Australia’s Northern Territory have started industrial action as part of an ongoing dispute over pay and conditions, according to the Offshore Alliance.

Ichthys LNG strike called off

Japan's Inpex confirmed on Tuesday that workers on the Ichthys liquefied natural gas (LNG) export project will not strike on Wednesday and Thursday as previously planned.

Ichthys LNG strike expected to start next week

Japan's Inpex confirmed on Monday that it has received notice to strike from unions representing its workers on the Ichthys liquefied natural gas (LNG) export project.

Inpex: Ichthys terminal sent 43 LNG cargoes in January-April

Japan’s Inpex has shipped 43 LNG cargoes from its Ichthys export plant in Australia in the first four months of this year, up by two shipments compared to the year before.