Baron mulls floating LNG project off Timor-Leste

UK-listed Baron Oil is planning to develop a floating LNG production project based on gas resources from its Chuditch PSC located about 185 kilometers south of Timor-Leste, or East Timor.

SundaGas, a unit of Baron, is the operator of the Chuditch PSC and holds a 75 percent interest in the Chuditch PSC (TL-SO-19-16).

The Timor-Leste state oil company Timor Gap holds the remaining 25 percent interest.

The Chuditch PSC is located about 100 kilometers east of the producing Bayu-Undan field, and 50 kilometers south of the Greater Sunrise potential development in water depths of 50-100 meters, according to Baron.

Santos and its partners are supplying Bayu-Undan gas to the Darwin LNG plant in Australia, while Woodside has been working with Timor-Leste for years to agree on the development of the Greater Sunrise field.

Chuditch resources

Baron reported in a statement this week “significant increases” in its aggregate gas-in-place and recoverable gas resource estimates for the Chuditch PSC.

The firm said best case aggregate gross gas-in-place estimate reaches about 5,500 Bcf versus an equivalent estimate of 3,889 Bcf prior to 3D seismic data reprocessing.

Moreover, the firm reported best case recoverable resource estimate of 3,625 Bcf, using preliminary gas recovery factors of between 50 percent and 75 percent, versus an equivalent estimate of 2,924 Bcf prior to 3D seismic data reprocessing.

Baron said the Chuditch-1 gas discovery best case recoverable resource estimate of 1,350 Bcf “is materially larger and may independently represent a liquefied natural gas (LNG) scale resource.”

Baron mulls floating LNG project off Timor-Leste
Image: Baron Oil

“Hybrid floating and platform LNG system”

“As the preliminary subsurface interpretation is indicating an uncomplicated structural configuration for Chuditch, and subject to an ongoing revision of the Chuditch engineering concept study, a simpler field development concept is likely,” the firm said in the update.

The apparent increase in gas resources in the Chuditch-1 discovery itself suggests that a single appraisal well would suffice to determine commerciality of the project without the need for immediate follow-on exploration wells, it said.

Multiple potential export solutions for gas have been previously identified which are not dependent on any single concept or route, according to Baron.

“The fastest development and export option is expected to be to utilize a hybrid floating and platform LNG system, which does not require export pipelines or border crossings,” the firm said.

CCS plans, first production in 2028

Baron said it had started a revision of the Chuditch engineering concept study.

The firm expects that this work would illustrate and quantify a fast-track development pathway that targets first production in 2028.

Baron said its management estimates of project economics “continue to be attractive at current and long-term average gas prices in Asia.”

In addition, development strategies for handling carbon dioxide could include carbon capture and storage (CCS) at Bayu-Undan or for disposal within the Chuditch PSC.

“SundaGas aspires to achieve net zero LNG through long-term supply arrangements with buyers that have an effective Scope 3 strategy,” Baron said.

Most Popular

GTT CEO: LNG carrier replacement market poised for significant growth

Choimet officially took over as GTT CEO in June this year and has since then been on the road...

Japan’s November LNG imports drop 5.3 percent

The country’s LNG imports decreased to 5.05 million tonnes last month. LNG imports also dropped compared to 5.29 million tonnes...

Monjasa in UAE LNG bunkering move

Monjasa said on Wednesday it introduces the UAE’s first dedicated LNG bunkering vessel, Green Zeebrugge. Previously known as Engie Zeebrugge,...

More News Like This

Santos seals long-term LNG supply deal with Japan’s Shizuoka Gas

Santos said on Thursday the long-term SPA will supply between 0.35 and 0.4 million tonnes per annum of LNG...

Santos: Barossa project almost 84 percent complete

Santos said in its investor update on Tuesday that the project was 83.5 percent complete as at October 31,...

Santos: Angore project boosts PNG LNG

Santos announced the completion of the project worth about $1.2 billion in a statement on Tuesday. Angore has performed "strongly"...

Kumul gets advance payment from Chevron for PNG LNG cargoes

Kumul said in a statement it recently closed an agreement with Chevron USA (Singapore Branch) that will further Kumul’s...