LNG exports from the Gladstone port in Australia’s Queensland were almost flat in February when compared to the same month in the year before, according to Gladstone Ports Corporation.

Last month about 1.92 million tonnes of LNG left the three Gladstone terminals on Curtis Island, down 2.7 percent when compared to 1.97 million tonnes in the same month in 2020, GPC’s data shows.

This equals 30 LNG cargoes and compares to 30 shipments in February 2021.

Most of these exports or 986,783 tonnes landed in China, marking a drop when compared to 1.42 million tonnes last year.

The rest of Gladstone LNG exports in February went to South Korea, Singapore, Japan, and Malaysia, the data shows.

Gladstone LNG exports rose 6.8 percent in January to about 2.05 million tonnes, GPC said last month.

During the entire year of 2021, Curtis Island LNG plants dispatched 23.34 million tonnes or 356 cargoes of LNG, a rise of 4.3 percent compared to 2020.

Curtis Island is home to the Santos-operated GLNG plant, the ConocoPhillips-led APLNG terminal, and Shell’s QCLNG facility. These are the only LNG export facilities on Australia’s east coast.

Most Popular

Energy Transfer’s Lake Charles LNG secures DOE extension

Texas-based Energy Transfer has secured a permit extension from the US DOE to start exports from its proposed Lake Charles LNG export facility in Louisiana.

Shell adds another LNG carrier to its fleet

A unit of UK-based LNG giant Shell has added another chartered liquefied natural gas carrier to its fleet.

Santos CEO expects Papua LNG FID in early 2026

France's TotalEnergies and its partners plan to take a final investment decision on the Papua LNG export project in Papua New Guinea in the first quarter of 2026, according to Santos CEO Kevin Gallagher.

More News Like This

Shell adds another LNG carrier to its fleet

A unit of UK-based LNG giant Shell has added another chartered liquefied natural gas carrier to its fleet.

Origin reports steady APLNG revenue

The Australia Pacific LNG project logged steady revenues in the fiscal year ending June 30 from the prior year, mainly due to higher LNG volumes as the plant operated well above nameplate capacity following the LNG vessel power outage incident in the prior year, according to shareholder Origin Energy.

Gladstone LNG exports climb in July

Liquefied natural gas (LNG) exports from the Gladstone port in Australia’s Queensland rose in July compared to the same month last year, according to the monthly data by Gladstone Ports Corporation.

Santos says Barossa project 97 percent complete

The Barossa gas project, which will supply feed gas to the Santos-operated Darwin LNG plant, is 97 percent complete and remains on target for first production in the third quarter of 2025, according to Australia's Santos.