Santos: Barossa gas project more than 70 percent complete

The Barossa gas project, which will supply feed gas to the Santos-operated Darwin LNG plant, is more than 70 percent complete and “on track” for first production in the third quarter of 2025, according to Australia’s Santos.

Santos chair Keith Spence and managing director and CEO Kevin Gallagher revealed this during the company’s annual general meeting held on April 11.

Back in 2021, Santos took a final investment decision for its $3.6 billion Barossa project.

Natural gas will be extracted from the Barossa field, located in Commonwealth waters about 285 kilometers offshore north-north west from Darwin, and transported via a pipeline to the existing Darwin LNG facility.

In November last year, the last LNG cargo produced from the Bayu-Undan gas field has sailed from the Santos-operated Darwin LNG plant in Australia’s Northern Territory.

The final LNG shipment from Bayu-Undan left the 3.7 mtpa Darwin LNG plant at Wickham Point on November 11.

The Darwin LNG plant launched operations in 2006 and the facility is now being readied for the next 20 years, in preparation for the start of Barossa gas production in 2025.

To prepare for Barossa gas, Santos is working on the Darwin LNG life extension project.

The Darwin LNG plant life extension work is now “well underway” ahead of first gas from
Barossa next year, Gallagher said during the annual meeting.

He said the Barossa gas project itself is “more than 70 percent complete and will backfill Darwin LNG for 15 to 20 years.”

Gallagher said in February that the Barossa project was 67.4 percent complete.

Expanding LNG portfolio

Moreover, the first Barossa well “has been completed and pleasingly, initial well flow rates are in line with expectations and carbon dioxide content is at the low end of the expected range,” Gallagher said.

Spence said during the meeting that Santos is currently drilling the second of six wells, while pipelaying is nearing completion.

He said that subsea facilities installation is “well under way”, and that thirteen of the 16 topside modules have now been installed on the floating production storage and offtake vessel.

At full production rates, Barossa is expected to add 1.8 million tonnes per annum to Santos’
expanding LNG portfolio.

Besides Darwin LNG, Santos operates the GLNG terminal on Curtis Island off Gladstone and has a a stake in the PNG LNG project.

“Barossa is a world-class LNG asset designed to utilize existing infrastructure at Darwin LNG to deliver a low-cost, reliable, long-term source of supply to Japan and Korea,” Gallagher said.

Most Popular

Another steam LNG carrier sold for demolition

An NYK-managed steam liquefied natural gas (LNG) carrier has been sold for demolition, according to brokers.

NFE seals Puerto Rico LNG supply deal

NFE said in a statement that the contract is currently under review for approval by the Financial Oversight and...

Canada approves Ksi Lisims LNG project

According to a statement on Monday, Julie Dabrusin, Minister of Environment and Climate Change, issued her decision under the...

More News Like This

Adnoc-led consortium withdraws $18.7 billion bid for Santos

A consortium led by Adnoc's investment unit, XRG, has withdrawn its $18.7 billion takeover offer for Australian LNG player Santos.

Santos CEO expects Papua LNG FID in early 2026

France's TotalEnergies and its partners plan to take a final investment decision on the Papua LNG export project in Papua New Guinea in the first quarter of 2026, according to Santos CEO Kevin Gallagher.

Santos further extends exclusivity period for Adnoc takeover

Australian LNG player Santos has further extended the exclusivity period for its proposed $18.7 billion takeover by a consortium led by Adnoc's investment unit, XRG.

Santos says Adnoc takeover deal delayed

Australia LNG player Santos said on Tuesday that a consortium led by Adnoc's investment unit, XRG, would not be able to finalize the previously announced $18.7 billion takeover bid for another four weeks.