Santos: Barossa gas project more than 70 percent complete

The Barossa gas project, which will supply feed gas to the Santos-operated Darwin LNG plant, is more than 70 percent complete and “on track” for first production in the third quarter of 2025, according to Australia’s Santos.

Santos chair Keith Spence and managing director and CEO Kevin Gallagher revealed this during the company’s annual general meeting held on April 11.

Back in 2021, Santos took a final investment decision for its $3.6 billion Barossa project.

Natural gas will be extracted from the Barossa field, located in Commonwealth waters about 285 kilometers offshore north-north west from Darwin, and transported via a pipeline to the existing Darwin LNG facility.

In November last year, the last LNG cargo produced from the Bayu-Undan gas field has sailed from the Santos-operated Darwin LNG plant in Australia’s Northern Territory.

The final LNG shipment from Bayu-Undan left the 3.7 mtpa Darwin LNG plant at Wickham Point on November 11.

The Darwin LNG plant launched operations in 2006 and the facility is now being readied for the next 20 years, in preparation for the start of Barossa gas production in 2025.

To prepare for Barossa gas, Santos is working on the Darwin LNG life extension project.

The Darwin LNG plant life extension work is now “well underway” ahead of first gas from
Barossa next year, Gallagher said during the annual meeting.

He said the Barossa gas project itself is “more than 70 percent complete and will backfill Darwin LNG for 15 to 20 years.”

Gallagher said in February that the Barossa project was 67.4 percent complete.

Expanding LNG portfolio

Moreover, the first Barossa well “has been completed and pleasingly, initial well flow rates are in line with expectations and carbon dioxide content is at the low end of the expected range,” Gallagher said.

Spence said during the meeting that Santos is currently drilling the second of six wells, while pipelaying is nearing completion.

He said that subsea facilities installation is “well under way”, and that thirteen of the 16 topside modules have now been installed on the floating production storage and offtake vessel.

At full production rates, Barossa is expected to add 1.8 million tonnes per annum to Santos’
expanding LNG portfolio.

Besides Darwin LNG, Santos operates the GLNG terminal on Curtis Island off Gladstone and has a a stake in the PNG LNG project.

“Barossa is a world-class LNG asset designed to utilize existing infrastructure at Darwin LNG to deliver a low-cost, reliable, long-term source of supply to Japan and Korea,” Gallagher said.

Most Popular

Venture Global wraps up $2.25 billion senior notes offering

US LNG exporter Venture Global has completed its previously announced $2.25 billion offering of senior secured notes.

US weekly LNG exports rise to 34 shipments

US liquefied natural gas (LNG) plants sent 34 cargoes during the week ending June 10, up five cargoes from the week before, according to the Energy Information Administration.

Indonesia’s Sillo Maritime buys LNG carrier for $65 million

Indonesia's Sillo Maritime has purchased a 2009-built liquefied natural gas (LNG) carrier for $65 million.

More News Like This

Japan’s Jera gets first Barossa LNG cargo at Futtsu terminal

Japan’s power firm and LNG trader, Jera, has received its first Darwin LNG cargo produced from Australia's Barossa gas field at the Futtsu LNG terminal in Japan.

Santos takes FID on Agogo project in Papua New Guinea

Australian LNG player Santos has taken a final investment decision to proceed with the Agogo production facility tie-in project in Papua New Guinea, following approval by the ExxonMobil-led PNG LNG joint venture.

Santos: Barossa FPSO to start ramping up production next week

Australian LNG player Santos expects the Barossa floating storage and offloading facility (FPSO) to start ramping up production in the next week, with LNG production at the Darwin plant following thereafter.

JGC, Hyundai E&C secure Papua LNG EPC contract

Japan’s JGC and South Korea’s Hyundai Engineering & Construction have been selected as the engineering, procurement, and construction (EPC) contractor for the TotalEnergies-led Papua LNG project in Papua New Guinea. The final EPC contract award is expected after the project's final investment decision (FID) in 2026, according to JGC.