Shell’s Prelude FLNG to remain offline after fire

Shell’s giant Prelude FLNG located offshore Australia will likely remain offline for a while following an incident earlier this month.

A Shell spokesperson told LNG Prime earlier this month that the firm had suspended production after an incident on December 2.

The spokesperson said that smoke detected in an electrical utility area had triggered the automatic fire detection and management systems on board the Prelude FLNG facility located some 475 km from Broome in Western Australia.

Shell had also decided to evacuate the majority of workers on board the FLNG as the unit requires only a skeleton crew during a production shutdown.

NOPSEMA report

The following morning, Australian offshore regulator NOPSEMA had launched an investigation into the incident, it said in a report dated December 23.

The Shell Australia-owned and operated Prelude FLNG facility experienced an unplanned event that resulted in a complete loss of power at the facility, which subsequently led to unreliable and intermittent power availability over 3 days, the regulator said.

According to NOPSEMA, Shell made multiple attempts during this period to re-establish reliable power.

The regulator said it had established regular contact with Shell onshore management for updates on the offshore emergency situation and the activities underway to respond and recover, as the loss of power had impacted the “habitation and working conditions of the personnel on the facility.”

“By December 6, 2021, the failure to restore reliable power was seen to represent an ongoing impact and risk to the health and safety of the personal on the facility and NOPSEMA arranged to visit the facility,” it said.

FLNG visit

The regulator’s inspectors visited the FLNG on December 8, returning two days later.

Moreover, the inspectors concluded that the operator “did not have a sufficient understanding of the risks of the power system on the facility, including failure mechanisms, interdependencies and recovery,” NOPSEMA said.

The regulator said that power failures directly impacted emergency response capability, operation of safety critical equipment, and evacuation of personnel by helicopter or boat.

Also, the failures impacted habitability of the facility for the personnel on board. This included essential services such as lighting, safety systems, communication systems, potable water systems, sewage treatment and HVAC.

NOPSEMA said that seven people were treated for heat-related conditions.

The regulator said that Shell is working to determine the cause(s) of the power system
issues that led to this incident.

However, the proposed scope of the investigation “does not provide for a thorough review of the evidence and root cause analysis of the entire series of events experienced during the incident and a review of the risks for future similar incidents and actions to mitigate them,” NOPSEMA said.

Prelude FLNG to remain shut until it is safe

Following the investigation, NOPSEMA has given four directions to Shell.

Under the first direction, Shell has to carry out a review or reviews of the incidents and associated consequences that occurred at the Prelude FLNG facility from December 2-6, including the issues identified in the NOPSEMA investigation report.

Based on the findings of the reviews from the first direction, Shell has to develop a detailed plan, schedule and commitment to timely implementation of all necessary corrective actions, NOPSEMA said.

“Prior to hydrocarbon production commencing, demonstrate to NOPSEMA’s satisfaction that the facility can safely recover essential power and associated essential services following a loss of power, and that the safety systems and essential support systems operate to maintain safety of personnel,” the regulator said.

As part of the fourth direction, Shell will have to send reports to the regulator.

“On the first business day of each month commencing March 2022 provide an update to NOPSEMA detailing progress under Directions 1 and 2 until NOPSEMA is satisfied under Direction 3,” the regulator said.

Production problems continue

Shell’s chief executive Ben van Beurden said earlier this year that the firm was working to bring Prelude to full production following a long shutdown due to an electrical trip in February last year.

To remind, the giant floating LNG producer shipped the first cargo in almost a year in early January followed by the second shipment later the same month.

Prelude delivered its first cargo in June 2019 after several start-up delays. The FLNG has the capacity to produce 3.6 mtpa of LNG, 1.3 mtpa of condensate, and 0.4 mtpa of LPG.

Shell operates the floating facility with a 67.5 percent stake. Japan’s Inpex holds a 17.5 percent stake, Korea’s Kogas 10 percent, and Taiwan’s CPC holds 5 percent.

Most Popular

Woodside terminates Commonwealth LNG SPA

Australian LNG player Woodside has terminated its two LNG sale and purchase agreements with US LNG terminal developer Commonwealth LNG.

Energy Transfer seals Lake Charles LNG supply deals

Texas-based Energy Transfer has signed new supply deals for its planned Lake Charles LNG export facility in Louisiana as it works to take a final investment decision by the end of this year, according to its management.

Thailand in Alaska LNG talks

Thailand's PTT and Egco will engage in further discussions to potentially participate in the development and buy volumes from the planned Alaska LNG project, according to Thailand's Ministry of Energy.

More News Like This

Peru LNG terminal shipped three cargoes in April

Peru LNG’s liquefaction plant at Pampa Melchorita has shipped three liquefied natural gas cargoes in April due to restrictions on the transportation system, according to operator Hunt Oil.

CFO: Shell on track to ship first LNG Canada cargo in middle of 2025

LNG giant Shell remains on track to deliver the first liquefied natural gas cargo from its LNG Canada export terminal in Kitimat in the middle of this year, according to Shell's finance chief, Sinead Gorman.

Shell’s Q1 profit reaches $5.58 billion, LNG sales drop

LNG giant Shell reported a drop in adjusted earnings in the first quarter of 2025, while its LNG sales also decreased compared to the same quarter in 2024.

Venture Global launches Calcasieu Pass LNG commercial ops

US LNG exporter Venture Global LNG has launched commercial operations at its Calcasieu Pass LNG terminal in Louisiana, some 68 months from its final investment decision and 38 months after production start.